What we do for shortage of material received?

AnswerBot
1y

When faced with a shortage of material received, we take immediate action to address the issue and minimize any negative impact.

  • Contact the supplier to inform them about the shortage and request immed...read more

Kamlesh Valand
1mo
Construction material. Receive
MAHENDRA PRATAP SINGH
1mo
works at
Railway project ( EDFCLOT-301 )
When facing a shortage of materials received, consider the following steps: 1. Verify the receipt: Double-check the delivery documents and inventory records. 2. Notify the supplier: Inform the supplie...read more
Anonymous
2mo
Indent issue to purcurment deprt arrejent bases
Gadi Mohammed Baba
3mo
If there is a material shortage at the site, do not sign the received documents initially. First, contact the transporter and inform them about the material shortage. Then, raise a complaint with the ...read more
punit Kumar
3mo
If any time face the shortage of received material first of all inform the transporter and note it in return and receipt copy and after then informed to vendor by mob or mail about it.
D Prakash
3mo
When we rec'd the materials that time check the qty, if any short, immediately we informed to vendor and collect the credit note for further process
Sasi Kumar
6mo
Before I checking which work so before I checking material and order before 2days
Balaram Debbarma
8mo
Stop a work and try to quickly arrange the the shortage of a materials or find out why the material quantity is short delivered.
JITENDRA KUMAR RAY
10mo
qty by checked after driver signatur & mobil.no.write down after shortage qty
Akash kumar Singh
1y
To address a shortage of material received, follow these steps: 1. Document the Shortage 2. Notify Suppliers Immediately 3. Request Immediate Action 4. Update Inventory Records 5. Evaluate Impact on O...read more
Anonymous
1y

Yes, do not over focus on cost downing

Sagar Sinha
1y

According to material consumption chart.

Loganathan Natarajan
1y

First of all I should inform my reporting manager and I'll start the work with that available materials parallelly I will inform my QS and my supplier what happen to this minimum of material was deliv...read more

A RAJENDRAN
1y

Arrange get it speedy,at the same plan the work accordingly without affecting the progress

rohit rajput
1y
  1. ANTICIPATING SUPPLY & demand, be friends with your friends with your suppliers

  2. do not over focus on cost downing

  3. explore hidden excess capacities in the market

  4. having a second supplying source

Anonymous
1y

For shortage of materials, first of all , will have to make list of materials shortages itemwise or product wise immediately on the spot

so as to enable us to make easy follow up and immediate action ...read more

Anonymous
1y

Reinforcement and cement

Jayesh Banjara
1y

as per required mateiral as per drawings no shortage material. reccevied material reconciliation and after shortagd material list ready and as per Detials missing material.

praveen sharma
2y

According to plan material will short so check root couse and confirm it after then reindent material.

Divyanshu jonwal
2y

Prepared execution design and drawings and planning to other without materials works as a foundation civil work and planning for BOQ preparation and planning for bulk to bulk works.

Divyanshu jonwal
2y

When materials will be short we will planning to prepared total materials requirements and survey plan in bulk work in other words as foundation preparation design and drawings preparation for executi...read more

Add answer anonymously...
Tata Projects Deputy Manager Interview Questions
Stay ahead in your career. Get AmbitionBox app
qr-code
Helping over 1 Crore job seekers every month in choosing their right fit company
65 L+

Reviews

4 L+

Interviews

4 Cr+

Salaries

1 Cr+

Users/Month

Contribute to help millions
Get AmbitionBox app

Made with ❤️ in India. Trademarks belong to their respective owners. All rights reserved © 2024 Info Edge (India) Ltd.

Follow us
  • Youtube
  • Instagram
  • LinkedIn
  • Facebook
  • Twitter