Site Engineer

Site Engineer Interview Questions

Updated 28 Feb 2024

Most Searched Companies

1383 results found

Sort By: 

Popularity

Interview Questions

+16 interview questions

Interview Questions

  • Q1. design? 1.what is ASD in steel design? 2.what is special consideration in steel structure? 3. What is objective of design in steel structure ?4which what is code is used for steel structure? 5. What are structure steel member

    View answer (1)
  • Q2. 1.what do you mean by steel structure design? 2.what are the steel of structure design? 3.what are the three design methods?4.fer steel structure? 5.which objective of in steel structure

    View answer (1)
  • Q3. 1.what is the minimum thickness of gusset plate?2.what do you mean by steel structure design? 3.fer steel structure? 4.what is asd in steel design?

    View answer (1)
  • Q4. 1.what are structure steel member? 2.what is the minimum thickness of gusset plate

    View answer (1)
  • Q5. There are three different methods for design of steel structure. (Simple design) (continuous design) (semi-continuous steel design)

    View answer (1)
  • Q6. 1.which specification used for analysis and design of steel design?

    View answer (1)
  • Q7. 1.what are the three design methods

    View answer (1)

Interview Questions

  • Q1. Asking to me...... Only civil engineering questions

    View answer (1)
  • Q2. What is hydro power test of DI pipes...?

    Add Answer
  • Q3. Only waste water treatment plants related questions

    Add Answer
  • Q4. Only waste water treatment plants related questions

    Add Answer
  • Q5. Q:- What is the procedure for fit up inspection? Ans:- Base metal Classification, cleaning, Alignment, Root gap, root face, Bevel angle & mismatch or overlap.

    View answer (1)
  • Q6. What is the hydrotest pressure? Ans:- 1.5 times of design pressure.

    View answer (1)
  • Q7. About simulation, GIS mapping, calculation of SR as per flow rate and potential, Integrated CNG stations, specification of MDPE, GI, welded riser, type of joint, specification of Fusion machine, and projects achievements etc.

    Add Answer
  • Q8. RCC spun related question

    Add Answer
  • Q9. About the CGD ?

    Add Answer
  • Q10. Technical questions related pipeline

    Add Answer

Interview Questions

  • Q1. Grade of concrete which was used, IS codes, questions mostly related to current working project, all technical.

    Add Answer
  • Q2. What is the slump required & which type of admixture was used

    Add Answer
  • Q3. What is the clearance between girder and ground

    View answer (1)
  • Q4. Socketing Criteria For Piles in Hard Rock

    Add Answer
  • Q5. Difference between CHSL and Pile Integrity Test

    Add Answer
  • Q6. Basic civil engineer question which is generally used and follow at site.

    Add Answer
  • Q7. How to prevent from Pile bent

    View answer (1)
  • Q8. How to check the quality of concrete

    Add Answer
  • Q9. Experience and Salary Releated Questions

    Add Answer
  • Q10. Pile Foundation Execution Process

    Add Answer

+7 interview questions

Interview Questions

+8 interview questions

Interview Questions

  • Q1. Unit of measurement of chowkhats, doors, plastering, painting Formula to find unit weight of steel Unit weight of 8mm, 10mm, 12mm bars Quanity of cement, sand and coarse aggregate required for one cubic meter of M20 concrete Number of bars required for 4m length column. Assume centre to centre spacing as 300mm

    Add Answer
  • Q2. Unit of measurement of chowkhats, doors, plastering, painting Formula to find unit weight of steel Unit weight of 8mm, 10mm, 12mm bars Quanity of cement, sand and coarse aggregate required for one cubic meter of M20 concrete Number of bars required for 4m length column. Assume centre to centre spacing as 300mm

    Add Answer
  • Q3. Introduce yourself

    Add Answer

Interview Questions

+9 interview questions

Interview Questions

  • Q1. 1)tell me 5 nos of IS code. 2)floor drop. 3) Gypsum activity procedure. 4)gypsum area consumption,density. 5) waterproofing procedure. 6)which area comes in toilet bath. 7)Is code for BBS. 8)kitchen platform size. 9)who to start your work on site. 10)before starting painting what was the procedure.which paint use,how much moisture allow before starting painting. 11)if moisture above 10%in Gypsum then what defects shows on that wall. 12)approved Safety helmet (EN397) EN means.ASTM full form,IS full form. 13)where fix safety belt when labour working on outer platform.

    View answer (1)

Interview Questions

  • Q1. Operation & Maintenance of BMS system, DGs sets, Cooling tower, HVAC system, AHUs, FCUs. Operation & Maintenance of Transformer, HT, LT, ACB, VCB, Control panels, lighting system. Operation & Maintenance of Elevator, WTP, STP, Fire Fighting system, Make the weekly & Monthly HSD & Energy Consumption Report and Training of all maintenance staff.

    Add Answer
  • Q2. Manpower Handling Vender Management LOTO Management Management Information Documentation Management Weekend & future Planning Client Co-Operation Fire Safety Management Store Management

    Add Answer

Interview Questions

+4 interview questions