What is variation clause, Price variation, value engineering, suspension as per FIDIC?

AnswerBot
2y
Explanation of variation clause, price variation, value engineering, suspension as per FIDIC.
Variation clause allows for changes in the scope of work.
Price variation allows for adjustments in contract...read more
Anonymous
1y
Variations may be initiated by the Engineer under sub-clause 13.3 [Variation Procedure] at any time before the issue of the taking -over Certificate for the work
Help your peers!
Add answer anonymously...
Hindustan Construction Company Contract Engineer interview questions & answers
A Contract Engineer was asked Q. Why is a price variation clause required in a contract?
A Contract Engineer was asked Q. According to FIDIC, what are the roles of the Employer, Engineer, and Contractor...read more
A Contract Engineer was asked Q. What are the differences between the FIDIC Red Book and Yellow Book?
Popular interview questions of Contract Engineer
A Contract Engineer was asked Q1. Why is a price variation clause required in a contract?
A Contract Engineer was asked Q2. According to FIDIC, what are the roles of the Employer, Engineer, and Contractor...read more
A Contract Engineer was asked Q3. What are the differences between the FIDIC Red Book and Yellow Book?
>
Hindustan Construction Company Contract Engineer Interview Questions
Stay ahead in your career. Get AmbitionBox app


Trusted by over 1.5 Crore job seekers to find their right fit company
80 L+
Reviews
10L+
Interviews
4 Cr+
Salaries
1.5 Cr+
Users
Contribute to help millions
AmbitionBox Awards
Get AmbitionBox app