Planning and Scheduling Engineer

20+ Planning and Scheduling Engineer Interview Questions and Answers

Updated 29 Jul 2025
search-icon

Asked in ExxonMobil

5d ago

Q. What is rebaseline, what is the process for changing the baseline, and at what stage should rebaseline occur, such as during the initial phase, midway, or at the final stage like commissioning?

Ans.

Rebaseline is the process of updating project baselines to reflect changes in scope, schedule, or resources.

  • Rebaseline is necessary when there are significant changes in project scope or timelines.

  • The process involves assessing current performance against the original baseline and determining new baseline metrics.

  • Rebaseline should occur at critical project phases, such as after major scope changes or midway through the project.

  • For example, if a project is delayed due to unfor...read more

Asked in ExxonMobil

1d ago

Q. What is the difference between planned value and earned value in project management, or are they the same?

Ans.

Planned value and earned value are key metrics in project management, representing different aspects of project performance.

  • Planned Value (PV) is the budgeted amount for work scheduled to be completed by a specific time.

  • Earned Value (EV) is the budgeted amount for work actually completed by that same time.

  • For example, if a project has a total budget of $100,000 and is scheduled to complete 50% of the work by month 6, the PV at month 6 is $50,000.

  • If by month 6, the project has...read more

Asked in ExxonMobil

5d ago

Q. What are the definitions of Cost Performance Index (CPI) and Schedule Performance Index (SPI), and how can they be measured?

Ans.

CPI and SPI are key performance indicators in project management, measuring cost efficiency and schedule adherence respectively.

  • Cost Performance Index (CPI) = Earned Value (EV) / Actual Cost (AC). A CPI > 1 indicates cost efficiency.

  • Example: If EV is $100,000 and AC is $80,000, then CPI = $100,000 / $80,000 = 1.25.

  • Schedule Performance Index (SPI) = Earned Value (EV) / Planned Value (PV). An SPI > 1 indicates ahead of schedule.

  • Example: If EV is $100,000 and PV is $120,000, the...read more

Asked in ExxonMobil

1d ago

Q. What are the different types of contracts, and which type would be most feasible for a company entering the market first?

Ans.

Various contract types exist, with fixed-price contracts often being most feasible for new market entrants.

  • 1. Fixed-Price Contracts: Set price for the project, beneficial for budgeting. Example: Construction projects with a defined scope.

  • 2. Cost-Plus Contracts: Reimburses costs plus a fee, suitable for uncertain projects. Example: Research and development projects.

  • 3. Time and Materials Contracts: Pays for time spent and materials used, flexible for evolving projects. Example:...read more

Are these interview questions helpful?

Asked in ExxonMobil

5d ago

Q. What are the methods for erecting a pipe on a plate, and what deliverables and levels should be considered when preparing the schedule?

Ans.

Methods for erecting pipes on plates include various techniques and require careful scheduling and deliverables.

  • Use of cranes for lifting and positioning pipes onto plates.

  • Utilization of pipe supports and brackets to secure pipes.

  • Implementation of welding techniques for permanent attachment.

  • Consideration of safety protocols during the erection process.

  • Scheduling should include milestones for each phase of the erection.

  • Deliverables may include erection plans, safety assessment...read more

Asked in ExxonMobil

4d ago

Q. What are the stages of planning in a new project, and how can progress be measured using Primavera P6?

Ans.

Planning a new project involves stages like initiation, planning, execution, and monitoring, with Primavera P6 for progress tracking.

  • 1. Project Initiation: Define project goals, scope, and stakeholders. Example: Conduct a feasibility study.

  • 2. Project Planning: Develop a detailed project plan including timelines, resources, and budget. Example: Create a Work Breakdown Structure (WBS).

  • 3. Scheduling: Use Primavera P6 to create a project schedule with tasks, durations, and depend...read more

Asked in ExxonMobil

1d ago

Q. What is an S curve, how can one prepare it using Primavera P6, and what constraints should be considered when using Primavera P6?

Ans.

An S curve visualizes project progress over time, showing cumulative costs or work against the planned schedule.

  • An S curve represents cumulative data, typically cost or progress, plotted against time.

  • To prepare an S curve in Primavera P6, use the 'Earned Value' feature to track project performance.

  • Select the appropriate data (e.g., planned vs. actual costs) and generate a report to visualize the S curve.

  • Consider constraints like resource availability, project deadlines, and b...read more

Asked in ExxonMobil

2d ago

Q. What is earned value, what is the difference between earned hours and planned hours, and how can progress be measured?

Ans.

Earned value is a project management technique to assess project performance by comparing planned and actual progress.

  • Earned Value (EV) measures the value of work actually performed up to a specific point in time.

  • Planned Hours (PH) are the total hours scheduled for a task or project, while Earned Hours (EH) represent the hours earned based on completed work.

  • For example, if a project was planned to take 100 hours and 50 hours of work were completed, the EV would reflect the va...read more

Share interview questions and help millions of jobseekers 🌟

man-with-laptop

Asked in ExxonMobil

6d ago

Q. What weightages are considered during phases such as Design and Engineering, as well as other activities?

Ans.

Weightages in planning include design complexity, resource availability, and risk assessment to ensure effective scheduling.

  • Design Complexity: More complex designs require more time and resources. For example, a skyscraper design involves intricate engineering.

  • Resource Availability: Assessing the availability of skilled labor and materials can impact timelines. For instance, delays in steel supply can affect construction.

  • Risk Assessment: Identifying potential risks during des...read more

Asked in Jio

5d ago

Q. 1.What is free float, what is total float and what is critical path ? 2.What is Earned value managment ?How many projects have you done ? 4. How you handle multiple projects at one time.

Ans.

Free float is the amount of time a task can be delayed without delaying the project. Total float is the amount of time a task can be delayed without delaying the project's critical path. Critical path is the sequence of tasks that determines the project's duration.

  • Free float is the time available for a task to be delayed without affecting the project's schedule.

  • Total float is the time available for a task to be delayed without affecting the project's critical path.

  • Critical pa...read more

Asked in ExxonMobil

4d ago

Q. What is the experience weightage in planning, scheduling, and costing, expressed as a percentage?

Ans.

Experience weightage in planning, scheduling, and costing varies by project but typically emphasizes planning and scheduling.

  • Planning: 40% - Critical for defining project scope and objectives.

  • Scheduling: 35% - Essential for timeline management and resource allocation.

  • Costing: 25% - Important for budget management and financial forecasting.

  • Example: In a construction project, planning might involve site assessments, scheduling includes Gantt charts, and costing covers material ...read more

Asked in ExxonMobil

3d ago

Q. How do you measure progress, and what factors do you consider when assessing progress on site?

Ans.

Progress measurement in planning and scheduling involves tracking milestones, resource allocation, and site conditions to ensure project success.

  • Milestone Tracking: Regularly assess the completion of key project milestones, such as foundation completion or structural framing, to gauge overall progress.

  • Resource Allocation: Monitor the availability and utilization of resources, including labor and materials, to ensure they align with the project schedule.

  • Site Conditions: Evalua...read more

Asked in ExxonMobil

1d ago

Q. What is the difference between the actual budget, planned budget, and baseline budget?

Ans.

The actual budget reflects real expenditures, the planned budget is the initial forecast, and the baseline budget is the approved version.

  • Actual Budget: Represents the real costs incurred during the project. Example: If a project spent $100,000, that's the actual budget.

  • Planned Budget: The initial estimate of costs before the project starts. Example: A project may have a planned budget of $120,000.

  • Baseline Budget: The approved version of the planned budget, used for performan...read more

Asked in ExxonMobil

1d ago

Q. What is the estimated duration in months for the design, procurement, and erection of a pump?

Ans.

Estimated duration for pump design, procurement, and erection typically spans 6 to 12 months, depending on project complexity.

  • Design phase: 2-4 months for detailed engineering and specifications.

  • Procurement phase: 3-6 months for sourcing materials and equipment.

  • Erection phase: 1-2 months for installation and commissioning.

  • Complex projects may require additional time for regulatory approvals.

Asked in ExxonMobil

5d ago

Q. What is design engineering, and what stages are involved in the design process?

Ans.

Design engineering involves creating solutions through a structured process, ensuring functionality and feasibility.

  • 1. Problem Definition: Identify the need or problem to be solved, e.g., designing a new medical device.

  • 2. Research and Analysis: Gather information and analyze existing solutions, e.g., studying current prosthetic designs.

  • 3. Concept Development: Generate ideas and concepts, e.g., sketching multiple designs for a new product.

  • 4. Design Evaluation: Assess concepts ...read more

Asked in ExxonMobil

6d ago

Q. What is the process for raising material requirements and procuring materials in an organization?

Ans.

The process involves identifying needs, creating requisitions, sourcing suppliers, and managing delivery timelines.

  • Identify material requirements based on project specifications and schedules.

  • Create a material requisition document detailing quantities, specifications, and delivery timelines.

  • Submit the requisition to the procurement department for approval.

  • Source suppliers through market research or existing vendor lists, ensuring they meet quality and cost criteria.

  • Negotiate ...read more

Asked in ExxonMobil

5d ago

Q. What is a P&ID (Piping and Instrumentation Diagram)?

Ans.

A P&ID is a detailed diagram that shows the piping and instrumentation of a process system.

  • Represents the relationship between equipment, piping, and instrumentation.

  • Includes symbols for valves, pumps, tanks, and other components.

  • Used for design, operation, and maintenance of process systems.

  • Example: A P&ID for a chemical plant may show reactors, heat exchangers, and control systems.

  • Essential for safety and regulatory compliance in engineering projects.

Asked in ExxonMobil

1d ago

Q. What is system scheduling following the completion of construction?

Ans.

System scheduling post-construction involves planning maintenance, operations, and resource allocation for optimal performance.

  • Establishing a maintenance schedule to ensure equipment reliability, e.g., regular inspections of HVAC systems.

  • Allocating resources for ongoing operations, such as staffing for facility management.

  • Implementing a project handover plan to transition from construction to operational phase, ensuring all systems are functional.

  • Monitoring system performance...read more

Asked in ExxonMobil

6d ago

Q. How can you import cash flow reports into Primavera P6?

Ans.

Importing cash flow reports into Primavera P6 involves using Excel files and the import wizard for data integration.

  • Prepare your cash flow report in Excel format, ensuring it aligns with Primavera's data structure.

  • Use the 'Import' feature in Primavera P6, selecting 'Excel' as the file type.

  • Map the Excel columns to the corresponding Primavera fields during the import process.

  • Review the import summary for any errors or warnings before finalizing the import.

  • Example: If your cash...read more

Asked in ExxonMobil

5d ago

Q. How do you measure progress in Primavera P6?

Ans.

Progress in Primavera P6 is measured through various metrics like percent complete, earned value, and schedule variance.

  • Percent Complete: This indicates the percentage of work completed for each activity. For example, if an activity is 50% complete, it shows half of the work is done.

  • Earned Value Management (EVM): This technique compares the planned progress with actual progress. For instance, if the planned value is $10,000 and the earned value is $8,000, it indicates a perfo...read more

Asked in ExxonMobil

3d ago

Q. What are Greenfield and Brownfield projects?

Ans.

Greenfield projects are new developments on undeveloped land, while Brownfield projects involve redeveloping existing sites.

  • Greenfield projects start from scratch, like building a new factory on vacant land.

  • Brownfield projects involve renovating or upgrading existing structures, such as converting an old warehouse into apartments.

  • Greenfield examples include new highways or parks in untouched areas.

  • Brownfield examples include cleaning up and redeveloping contaminated industria...read more

Asked in Jio

3d ago

Q. What is free float and how can it be reduced?

Ans.

Free float is the amount of time an activity can be delayed without affecting the early start of its successor activity.

  • Free float is calculated by subtracting the duration of an activity from the amount of time available before its successor activity must start.

  • Reducing free float can be achieved by shortening the duration of the activity or by overlapping activities.

  • Free float is important in determining the critical path of a project and identifying potential delays.

  • For ex...read more

6d ago

Q. What is a Master Schedule and what are its different levels?

Ans.

A master schedule outlines project timelines, resources, and key milestones for effective planning and execution.

  • Defines overall project timeline and key deliverables.

  • Integrates various project components, such as tasks and resources.

  • Helps in resource allocation and workload balancing.

  • Example: In construction, it schedules phases like design, procurement, and construction.

  • Serves as a communication tool among stakeholders.

3d ago

Q. Levels of schedule

Ans.

Levels of schedule refer to the hierarchical structure of project schedules, detailing various phases and tasks.

  • 1. Master Schedule: Overview of the entire project timeline and major milestones.

  • 2. Phase Schedule: Breaks down the project into distinct phases, such as design, construction, and commissioning.

  • 3. Detailed Schedule: Provides a granular view of tasks, durations, and resources needed for each phase.

  • 4. Weekly/Daily Schedule: Focuses on short-term tasks and activities, ...read more

Interview Experiences of Popular Companies

Jio Logo
4.2
 • 2.4k Interviews
Tata Projects Logo
4.2
 • 510 Interviews
ExxonMobil Logo
3.8
 • 72 Interviews
View all
Interview Tips & Stories
Interview Tips & Stories
Ace your next interview with expert advice and inspiring stories
Planning and Scheduling Engineer Interview Questions
Share an Interview
Stay ahead in your career. Get AmbitionBox app
play-icon
play-icon
qr-code
Trusted by over 1.5 Crore job seekers to find their right fit company
80 L+

Reviews

10L+

Interviews

4 Cr+

Salaries

1.5 Cr+

Users

Contribute to help millions

Made with ❤️ in India. Trademarks belong to their respective owners. All rights reserved © 2025 Info Edge (India) Ltd.

Follow Us
  • Youtube
  • Instagram
  • LinkedIn
  • Facebook
  • Twitter
Profile Image
Hello, Guest
AmbitionBox Employee Choice Awards 2025
Winners announced!
awards-icon
Contribute to help millions!
Write a review
Write a review
Share interview
Share interview
Contribute salary
Contribute salary
Add office photos
Add office photos
Add office benefits
Add office benefits