Filter interviews by
I applied via Referral and was interviewed before Sep 2023. There was 1 interview round.
The stages in DPR of a road project include survey and investigation, planning and design, preparation of estimates, approval, and construction.
Survey and investigation to gather data on existing conditions
Planning and design to determine alignment, cross-section, and other details
Preparation of estimates for cost analysis
Approval from relevant authorities
Construction phase to execute the project
Top trending discussions
I'm drawn to this industry for its dynamic nature, opportunities for innovation, and the chance to make a meaningful impact on people's lives.
The industry is constantly evolving, which keeps my work exciting and challenging.
I am passionate about innovation; for example, advancements in technology can significantly improve efficiency.
I appreciate the opportunity to contribute to society, such as improving customer exper...
I appeared for an interview in Dec 2024, where I was asked the following questions.
In my previous role, I managed team operations, streamlined processes, and enhanced client relationships to drive business success.
Led a team of 10 in achieving a 20% increase in productivity through effective training and motivation.
Implemented a new project management tool that reduced project completion time by 15%.
Developed strong client relationships, resulting in a 30% increase in repeat business.
Conducted regula...
In my previous role as a Team Leader, I managed projects, coordinated teams, and improved operational efficiency.
Led a team of 10 in a project that increased productivity by 20%.
Implemented a new software tool that streamlined communication and reduced response time by 30%.
Conducted regular training sessions to enhance team skills and knowledge.
I appeared for an interview before Jun 2024, where I was asked the following questions.
I applied via Referral and was interviewed before Apr 2023. There was 1 interview round.
posted on 10 Oct 2024
posted on 10 May 2020
Wall plastering mix ratio is the proportion of materials used in the plaster mix.
Wall plastering mix ratio typically consists of cement, sand, and water.
A common mix ratio for wall plastering is 1:4, which means 1 part cement to 4 parts sand.
The amount of water added can vary depending on the desired consistency of the plaster mix.
What is new technology in civil work .
I applied via Naukri.com and was interviewed in Mar 2021. There was 1 interview round.
Shuttering quantity for slab and beam is calculated based on the area and dimensions of the structure.
Shuttering quantity for slab is calculated by multiplying the area of the slab by the height of the formwork.
Shuttering quantity for beam is calculated by multiplying the length of the beam by the height and width of the formwork.
The quantity of shuttering material required also depends on the type of formwork used, su...
posted on 9 Sep 2022
I applied via Campus Placement and was interviewed before Sep 2021. There were 2 interview rounds.
Answering questions related to Civil Site Engineering
Slump is a measure of the consistency of concrete
Concrete ratio refers to the proportion of cement, sand, and aggregate in the mix
Curves on roads are provided to ensure safe and smooth traffic flow
Construction joints are used to allow for expansion and contraction of concrete due to temperature changes
based on 1 interview experience
Difficulty level
Duration
based on 31 reviews
Rating in categories
Field Engineer
89
salaries
| ₹2 L/yr - ₹4.8 L/yr |
Assistant Highway Engineer
67
salaries
| ₹3 L/yr - ₹6.6 L/yr |
Assistant Bridge Engineer
43
salaries
| ₹3.6 L/yr - ₹6 L/yr |
Resident Engineer
37
salaries
| ₹9.6 L/yr - ₹18 L/yr |
Quantity Surveyor
30
salaries
| ₹4.8 L/yr - ₹6.6 L/yr |
Nasser S. Al Hajri Corporation
Navayuga Engineering Company
B.L. Kashyap & Sons
L & W Constructions