Asked in L&T Construction

Q. If a drawing specifies 12mm diameter rebar with 150mm spacing, and you only have 16mm rebar available, what would be the adjusted spacing for the 16mm rebar?
Spacing for 16mm dia rebar if 12mm dia rebar is not available.
Calculate the area of 12mm dia rebar and 16mm dia rebar.
Use the ratio of areas to find the spacing for 16mm dia rebar.
Spacing for 16mm dia rebar would be approximately 211 mm.
Ensure that the new spacing meets the required design standards.

Asked in B. G. Shirke Construction Technology

Q. How much load can adjustable props take for shuttering works?
The load taken by adjustable props for shuttering works depends on various factors.
The load capacity of adjustable props depends on their size and material.
The type of shuttering work being done also affects the load taken by adjustable props.
The load can vary from a few hundred kilograms to several tons.
Adjustable props are commonly used in construction to support formwork during concrete pouring.
The load taken by adjustable props should always be within their specified safe...read more

Asked in B. G. Shirke Construction Technology

Q. What are the different types of shuttering methods, and what are the advantages of each?
There are various types of shuttering methods used in construction, each with its own advantages.
Types of shuttering methods include timber, steel, aluminum, plastic, and fabric.
Timber shuttering is cost-effective and easy to work with, while steel shuttering is durable and reusable.
Aluminum shuttering is lightweight and easy to handle, while plastic shuttering is waterproof and easy to clean.
Fabric shuttering is flexible and can be used for complex shapes.
Advantages of shutt...read more

Asked in L&T Construction

Q. What was the minimum number of days for the Mivan shuttering slab cycle in your previous project?
The minimum number of days for the Mivan shuttering slab cycle in my previous project was 7 days.
The Mivan shuttering slab cycle typically takes 7-10 days to complete.
Efficient planning and coordination can help reduce the cycle time.
Using experienced labor and proper equipment can also speed up the process.

Asked in L&T Construction

Q. What type of safety measures do you follow during construction work?
We follow strict safety protocols to ensure the well-being of workers and prevent accidents.
We conduct regular safety meetings to discuss potential hazards and how to avoid them.
We provide personal protective equipment (PPE) such as hard hats, safety glasses, and gloves.
We implement fall protection measures such as guardrails, safety nets, and harnesses.
We ensure that all equipment and machinery are properly maintained and inspected.
We have emergency response plans in place a...read more

Asked in L&T Construction

Q. What is the complete process for documentation and obtaining all original certificates?
The process involves collecting, organizing, and verifying all necessary documentation and certificates.
Collect all required documents such as permits, licenses, and insurance certificates.
Organize the documents in a systematic manner for easy access and reference.
Verify the authenticity and validity of each certificate by cross-checking with issuing authorities.
Ensure all original certificates are obtained and stored securely for future reference.
Maintain a detailed record o...read more
Assistant Construction Manager Jobs


Asked in Larsen & Toubro Limited

Q. What is the tolerance for mismatch between two bolted flanges?
The tolerance between two mismatch bolted flanges refers to the allowable deviation in alignment or positioning of the flanges.
Tolerance is typically specified in terms of a maximum allowable gap or misalignment between the flanges.
It ensures that the flanges can still be bolted together securely even if they are not perfectly aligned.
The tolerance depends on the specific application and industry standards.
For example, in the oil and gas industry, the tolerance for mismatch b...read more

Asked in L&T Construction

Q. Tell me briefly about pipeline work.
Pipeline work involves the construction, maintenance, and repair of pipelines used for transporting fluids or gases.
Pipeline work includes excavation, welding, coating, and testing of pipelines.
Construction of pipelines involves laying pipes, installing valves, and building pump stations.
Maintenance work includes inspecting pipelines for leaks, corrosion, and other damage.
Repair work involves fixing leaks, replacing damaged sections of pipeline, and upgrading existing pipelin...read more
Share interview questions and help millions of jobseekers 🌟

Asked in Larsen & Toubro Limited

Q. What permits are required on a construction site in Qatar?
Permits available in construction field in Qatar include building permits, electrical permits, plumbing permits, and mechanical permits.
Building permits are required for new construction, renovations, and additions.
Electrical permits are needed for any electrical work on a construction site.
Plumbing permits are necessary for any plumbing installations or modifications.
Mechanical permits are required for HVAC systems and other mechanical work.
Other permits may include demoliti...read more

Asked in Larsen & Toubro Limited

Q. What is the rating of the highest-capacity transformer used in the project?
The highest transformer used in the project is rated at 5000 kVA.
The highest transformer used in the project has a rating of 5000 kVA.
Transformers are rated in terms of their capacity to handle electrical load.
Higher kVA rating indicates a larger capacity to handle electrical load.
Example: The highest transformer used in the project is a 5000 kVA transformer.

Asked in JSW Energy

Q. How do you approach project documentation and quality control in your engineering projects?
I prioritize thorough documentation and rigorous quality control to ensure project success and compliance with standards.
Establish a clear documentation plan at the project's outset, detailing what needs to be recorded and how.
Utilize project management software to track progress, changes, and issues in real-time, ensuring all team members are aligned.
Conduct regular quality audits and inspections to identify potential issues early, such as checking materials against specific...read more

Asked in L&T Heavy Civil Infrastructure

Q. How do you maintain safety when working at heights?
Safety in height of work can be maintained by following safety protocols and using proper equipment.
Ensure workers are trained in safety procedures
Use proper safety equipment such as harnesses and helmets
Regularly inspect equipment and scaffolding
Implement a safety plan and enforce it strictly
Provide adequate lighting and signage
Monitor weather conditions and adjust work accordingly

Asked in L&T Construction

Q. What is the capacity of the WTP you have experience with?
I have experience working with WTPs with capacities ranging from 5 MGD to 50 MGD.
Worked on a 5 MGD WTP project in my previous role
Managed construction of a 20 MGD WTP in my current role
Assisted in the design of a 50 MGD WTP during my internship

Asked in Jio

Q. What are the details regarding optical fiber and its splicing?
Optical fiber is a medium for transmitting data as light pulses, with splicing connecting fiber segments for efficient communication.
Optical fibers are made of glass or plastic and transmit data using light.
Splicing is the process of joining two optical fibers together to maintain signal integrity.
There are two main types of splicing: fusion splicing (using heat) and mechanical splicing (using alignment fixtures).
Fusion splicing is preferred for its low loss and high strength...read more

Asked in L&T Heavy Civil Infrastructure

Q. What formalities should be checked before pouring concrete?
Formalities before concrete to be checked
Ensure proper reinforcement is in place
Check for proper formwork and its alignment
Verify the mix design and slump of concrete
Ensure proper curing measures are in place
Check for any obstructions or debris in the concrete placement area

Asked in Larsen & Toubro Limited

Q. What is a transposition tower in OHL?
A transposition tower in OHL is a structure used to change the position of conductors in overhead power lines.
Transposition towers are used to prevent power loss due to inductive reactance in long transmission lines.
They are typically taller than regular transmission towers to allow for the crossing of conductors.
Transposition towers are strategically placed along the transmission line to optimize power flow.
Example: In a 3-phase transmission line, transposition towers are us...read more

Asked in Larsen & Toubro Limited

Q. How can progress be improved in the erection of towers?
Improving progress in tower erection requires efficient planning, coordination, and communication.
Implement a detailed project schedule with clear milestones and deadlines.
Ensure proper coordination between different teams and subcontractors involved in the construction process.
Regularly monitor and track progress to identify any delays or bottlenecks early on.
Utilize technology such as Building Information Modeling (BIM) for better visualization and coordination.
Encourage op...read more

Asked in L&T Heavy Civil Infrastructure

Q. How do you check worker productivity?
To check worker productivity, monitor their output, track their progress, and evaluate their efficiency.
Monitor the quantity and quality of work completed by each worker.
Track the progress of tasks assigned to workers and compare it with the set deadlines.
Evaluate the efficiency of workers by analyzing their work methods and time management.
Use performance metrics and key performance indicators (KPIs) to measure productivity.
Provide feedback and coaching to workers to improve...read more

Asked in L&T Heavy Civil Infrastructure

Q. What is the de-shuttering period for shuttering activities?
De-shuttering period depends on various factors such as type of concrete, temperature, humidity, and strength required.
De-shuttering period is the time taken to remove the formwork or shuttering from the concrete after it has been poured.
The period varies depending on the type of concrete used, temperature, humidity, and strength required.
For example, for normal concrete, the de-shuttering period is usually 14-21 days, while for high-strength concrete, it can be up to 28 days...read more

Asked in L&T Construction

Q. Present project details with respect to cost, time, and specifications.
Overview of project cost, timeline, and specifications for effective management.
Cost: The total budget for the project is $1.5 million, covering materials, labor, and overhead.
Time: The project is scheduled to be completed in 12 months, with key milestones every 3 months.
Specifications: The project includes a 10,000 sq. ft. commercial building with LEED certification standards.
Example: For instance, the foundation work is budgeted at $300,000 and is expected to take 2 months ...read more

Asked in Larsen & Toubro Limited

Q. What codes and general work are involved on a construction site?
Codes are regulations that govern construction practices and safety standards on a job site.
Codes are established by local, state, and federal agencies to ensure that buildings are safe and meet certain standards.
Construction managers must be familiar with building codes and ensure that all work on the site complies with them.
General work on a site includes tasks such as scheduling, budgeting, coordinating with subcontractors, and overseeing the work of laborers and tradespeo...read more

Asked in L&T Construction

Q. Types of structures constructed
Various types of structures are constructed in construction industry.
Residential buildings such as apartments, villas, and houses
Commercial buildings such as offices, shopping malls, and hotels
Industrial buildings such as factories and warehouses
Infrastructure projects such as roads, bridges, and tunnels
Specialized structures such as sports stadiums, hospitals, and airports

Asked in Jio

Q. What is the FTTx network topology?
FTTx network topology refers to fiber optic networks that extend fiber closer to the end user, enhancing broadband connectivity.
FTTx stands for Fiber to the x, where 'x' can be home (FTTH), curb (FTTC), or building (FTTB).
FTTH connects fiber directly to residential homes, providing high-speed internet.
FTTC connects fiber to a street cabinet, with copper lines running to homes, balancing cost and performance.
FTTB connects fiber to a building, serving multiple tenants with high...read more

Asked in Larsen & Toubro Limited

Q. Can you achieve density greater than MDD?
Yes, achieving density more than Maximum Dry Density (MDD) is possible through proper compaction techniques and materials.
Achieving density more than MDD is possible by using vibratory compactors to increase soil compaction.
Proper moisture content in the soil is crucial for achieving higher density than MDD.
Using suitable materials like crushed stone or gravel can help in achieving higher density levels.
Regular testing and monitoring of compaction levels is essential to ensur...read more

Asked in Khansaheb Civil Engineering LLC

Q. How do you execute work on a construction site?
To execute work at site, proper planning, coordination, supervision, and communication are essential.
Develop a detailed project plan outlining tasks, timelines, and resources.
Coordinate with subcontractors, suppliers, and other stakeholders to ensure timely delivery of materials and services.
Supervise work progress on site to ensure quality and safety standards are met.
Communicate effectively with the project team to address any issues or changes in plans.
Regularly inspect th...read more

Asked in B. G. Shirke Construction Technology

Q. Methodology for all finishing activities
The methodology for finishing activities involves planning, coordination, and attention to detail.
Create a detailed schedule for finishing activities
Coordinate with subcontractors and suppliers to ensure timely delivery of materials
Ensure quality control measures are in place and followed
Conduct regular inspections to identify and address any issues
Communicate regularly with the project team to ensure everyone is on the same page
Examples: painting, flooring, cabinetry install...read more

Asked in Larsen & Toubro Limited

Q. Tests for coarse aggregate & fine aggregate
Tests for coarse aggregate & fine aggregate include sieve analysis, specific gravity, absorption, and particle shape.
Sieve analysis is used to determine the particle size distribution of aggregates.
Specific gravity test helps in identifying the density of the aggregates.
Absorption test measures the amount of water absorbed by the aggregates.
Particle shape test evaluates the shape of the aggregate particles.
Examples: ASTM C136 for sieve analysis, ASTM C127 for specific gravity...read more

Asked in L&T Construction

Q. How are the pipes welded?
Pipes are welded using various techniques such as arc welding, gas welding, and electric resistance welding.
Arc welding involves using an electric arc to melt the edges of the pipes and then joining them together.
Gas welding uses a flame produced by burning a mixture of fuel gas and oxygen to heat the pipes and create a molten pool for joining.
Electric resistance welding passes an electric current through the pipes, generating heat and causing them to fuse together.
Other tech...read more

Asked in Cheema Boilers

Q. How many types of boilers are there?
There are two main types of boilers: fire tube boilers and water tube boilers.
Fire tube boilers have hot gases passing through the tubes which are surrounded by water. Examples include Scotch marine boilers.
Water tube boilers have water flowing inside the tubes while hot gases surround them. Examples include Babcock and Wilcox boilers.

Asked in Larsen & Toubro Limited

Q. Please provide details of your experience and certificates.