Testing & Commissioning Engineer
40+ Testing & Commissioning Engineer Interview Questions and Answers

Asked in Alfanar

Q. What is the first step you would take if you observed an open secondary core of a CT while the feeder is still operating at a very low load?
The first step would be to investigate the cause of the secondary core of ct being open while the feeder is still working on very less load.
Check for any loose connections in the secondary core of ct
Inspect for any damage or faults in the secondary core of ct
Verify the load on the feeder to ensure it is within normal operating range
Consult with colleagues or experts for further troubleshooting steps
Asked in Yijie Technology

Q. What does an Electrical Engineer do?
An Electrical Engineer is a professional who designs, develops, and maintains electrical systems and equipment.
Electrical engineers work on various projects such as power generation, transmission, and distribution systems.
They design and analyze electrical circuits and systems to ensure their efficiency and safety.
They may specialize in areas such as power electronics, control systems, or telecommunications.
Electrical engineers often collaborate with other professionals, such...read more
Testing & Commissioning Engineer Interview Questions and Answers for Freshers

Asked in Laxmi Associates

Q. What is tan delta test of transformer and what is difference between GST and GSTg mode?
Tan delta test is used to measure insulation quality of transformer. GST and GSTg modes differ in the type of voltage applied.
Tan delta test measures the power loss in transformer insulation.
It helps to identify the presence of moisture, oil, or other contaminants in the insulation.
GST mode applies AC voltage to the transformer while GSTg mode applies DC voltage.
GSTg mode is more sensitive to insulation defects than GST mode.
The test is important for ensuring the reliability ...read more

Asked in Alfanar

Q. what is LIBBP,HIBBP Stability and sensitivity ?how you will impliment logic for one incomer and three outgoing feeders?how u will do BBP protection testing for this system ?
LIBBP and HIBBP stability and sensitivity refer to protection schemes for electrical systems. Implementing logic for one incomer and three outgoing feeders involves setting up coordination and communication between devices. BBP protection testing ensures the system operates correctly under fault conditions.
LIBBP and HIBBP stability and sensitivity are important for ensuring reliable protection of electrical systems.
Implementing logic for one incomer and three outgoing feeders...read more

Asked in Alfanar

Q. what is high voltage testing standard as per IEC?What will be testing voltage for 33kv system voltage.what testing kits your familiar to work on??
High voltage testing standard as per IEC includes testing voltage for 33kV system and familiar testing kits.
High voltage testing standard as per IEC includes IEC 60060-1 for high-voltage test techniques.
Testing voltage for 33kV system voltage is typically around 70-80kV.
Common testing kits for high voltage testing include insulation testers, voltage detectors, and partial discharge testers.

Asked in Laxmi Associates

Q. What is SFRA? and what we get the graph and how to read it?
SFRA stands for Sweep Frequency Response Analysis. It is a test used to analyze the frequency response of transformers.
SFRA is a non-invasive test used to detect winding deformation, core movement, and other mechanical issues in transformers.
The test involves sweeping a frequency range and measuring the response of the transformer.
The results are plotted on a graph, which can be used to identify any abnormalities in the transformer's frequency response.
The graph is read by an...read more
Testing & Commissioning Engineer Jobs

Asked in Alfanar

Q. what is ATS ?how you will configure ATS relay?what is trip selection.
ATS stands for Automatic Transfer Switch. It is used to automatically switch between primary and backup power sources.
ATS is a device used to switch between primary and backup power sources in case of power failure.
To configure ATS relay, you need to set the parameters such as voltage, frequency, and delay timings.
Trip selection refers to the setting that determines when the ATS will switch between power sources based on certain conditions.
Examples of trip selection criteria ...read more

Asked in Ohms Tech Engineers

Q. Are you aware of the tasks performed by an electrical engineer on-site in projects?
Yes, as a Testing & Commissioning Engineer, I am aware of the works being done on site by an electrical engineer.
As a Testing & Commissioning Engineer, I am responsible for ensuring that electrical systems are installed correctly and functioning properly.
I work closely with electrical engineers to test and commission various electrical systems, such as power distribution, lighting, and control systems.
I am familiar with the design, installation, and operation of electrical sy...read more
Share interview questions and help millions of jobseekers 🌟

Asked in Alfanar

Q. what is close block?why its necessary?why no fuse or mcb ON CT CIRCUIT?
Close block is a device used to short circuit the secondary of a current transformer (CT) during testing to prevent damage to the CT. No fuse or MCB is used on the CT circuit to avoid any interruption during testing.
Close block is used to short circuit the secondary of a CT during testing to prevent damage.
It ensures that the CT is not overloaded with excessive current during testing.
No fuse or MCB is used on the CT circuit during testing to avoid any interruption in the curr...read more

Asked in Ohms Tech Engineers

Q. Is solar or thermal energy production better?
It depends on various factors such as location, cost, efficiency, and environmental impact.
Solar energy is renewable and environmentally friendly, but it can be intermittent depending on weather conditions.
Thermal energy production can be more reliable and consistent, but it may have higher initial costs and environmental impacts.
The choice between solar and thermal energy production should be based on specific project requirements and goals.
Factors to consider include locati...read more

Asked in Alfanar

Q. How many years of experience do you have in substation networks?
I have 5 years of experience in substation network.
I have worked on various substation projects, including design, testing, and commissioning.
I have experience with different types of substation equipment and systems.
I have successfully completed multiple substation network projects on time and within budget.

Asked in Copeland

Q. How do digital input work How do digital output work What's plc scaning time How many type off timer in plc How do interlock with logic
Digital inputs and outputs in PLCs work by receiving or sending binary signals, PLC scanning time is the time taken for the PLC to complete one scan cycle, PLCs have different types of timers for various functions, Interlocking in PLCs is achieved through logical programming.
Digital inputs in PLCs receive binary signals from sensors or switches
Digital outputs in PLCs send binary signals to actuators or devices
PLC scanning time is the time taken for the PLC to complete one sca...read more
Asked in TSTS

Q. What are the relay types used in Indian railways?
The relay types used in Indian railways include electro-mechanical relays, solid-state relays, and microprocessor-based relays.
Electro-mechanical relays are commonly used in Indian railways for various applications.
Solid-state relays are used for their reliability and faster response times.
Microprocessor-based relays are used for advanced protection and control functions.
Examples of relay types used in Indian railways include the Westinghouse Type 'K' relay and the ABB RET670...read more

Asked in TCS

Q. What is the method to swap two numbers without using inbuilt functions?
Swapping two numbers without using inbuilt functions can be achieved using arithmetic operations.
Create a temporary variable to store one of the numbers.
Assign the value of the first number to the second number.
Assign the value of the temporary variable to the first number.

Asked in Ohms Tech Engineers

Q. What are the types of protection devices?
Protection devices are devices used to protect electrical systems from faults and overloads.
Overcurrent relays
Differential relays
Distance relays
Earth fault relays
Under voltage relays

Asked in NS Engineers

Q. What are the basic differences between electrical engineering and electronics engineering?
Electrical engineering deals with the generation, transmission, and distribution of electrical power, while electronics engineering focuses on electronic devices and circuits.
Electrical engineering primarily deals with large-scale power generation, transmission, and distribution systems.
Electronics engineering focuses on small-scale electronic devices, circuits, and systems.
Electrical engineering involves working with power generation plants, substations, and power lines.
Elec...read more

Asked in Alfanar

Q. what you know about alfanar saudi arabia ?
alfanar Saudi Arabia is a leading electrical engineering company in the Middle East.
alfanar Saudi Arabia specializes in electrical engineering solutions.
They offer a wide range of products and services including power distribution, control panels, and lighting solutions.
The company has a strong presence in the Middle East and has completed numerous projects in the region.
alfanar Saudi Arabia is known for its quality and reliability in the field of electrical engineering.
Asked in TSTS

Q. What are dispatch signals and receiving signals?
Dispatch signals are signals sent to initiate a specific action or task, while receiving signals are signals received to acknowledge or respond to a dispatched signal.
Dispatch signals are used to trigger a process or task.
Receiving signals are used to acknowledge or respond to a dispatched signal.
Dispatch signals can be in the form of electrical, digital, or wireless signals.
Receiving signals can be in the form of confirmation messages, acknowledgments, or feedback.
Dispatch s...read more

Asked in Johnson Controls

Q. What is Access control system, Fire alarm system,HVAC,VESDA,
Access control system, Fire alarm system, HVAC, VESDA are all essential components of building infrastructure.
Access control system: regulates who can enter or exit a building or specific areas within a building.
Fire alarm system: detects and alerts occupants of a building in case of fire or smoke.
HVAC (Heating, Ventilation, and Air Conditioning): controls the temperature, humidity, and air quality within a building.
VESDA (Very Early Smoke Detection Apparatus): provides early...read more

Asked in Incheon Motors

Q. Can you please introduce yourself?
I am a Testing & Commissioning Engineer with experience in various industries.
I have a degree in Electrical Engineering
I have worked on projects in the power generation industry
I have experience in testing and commissioning of electrical systems
I am familiar with various testing equipment and software
I have worked on projects in the oil and gas industry

Asked in Copeland

Q. How do relay & timer work How do interlock with relay
Relays and timers are electrical devices used to control the flow of electricity in a circuit. They work by opening or closing contacts based on specific conditions.
Relays are electromechanical devices that use an electromagnet to open or close electrical contacts. They are used to control high voltage circuits with low voltage signals.
Timers are devices that control the timing of events in a circuit. They can be digital or analog and are used to delay or sequence actions.
Int...read more

Asked in INVENTIVE SOFTWARE SOLUTIONS

Q. What is the difference between real power and apparent power?
Real power is the actual power consumed by a circuit, while apparent power is the combination of real power and reactive power.
Real power is the power actually consumed by a circuit to perform work.
Apparent power is the combination of real power and reactive power in a circuit.
Real power is measured in watts (W), while apparent power is measured in volt-amperes (VA).
The relationship between real power, apparent power, and power factor is given by the equation: Real Power = Ap...read more

Asked in Johnson Controls

Q. What is the scope of work in a chiller plant?
The scope of work in a chiller plant includes installation, maintenance, troubleshooting, and optimization of chiller systems.
Installation of chiller units and associated equipment
Regular maintenance to ensure optimal performance
Troubleshooting issues such as leaks, malfunctions, or inefficiencies
Optimizing chiller plant operations for energy efficiency
Ensuring compliance with safety and environmental regulations
Monitoring and controlling chiller plant parameters
Training staf...read more

Q. What types of electrical equipment are available?
Various types of electrical equipment include transformers, generators, circuit breakers, relays, and switchgear.
Transformers
Generators
Circuit breakers
Relays
Switchgear

Asked in Voltech

Q. Are you able to go to remote locations?
Yes, I am willing and able to go to remote locations for testing and commissioning work.
I have experience working in remote locations and am comfortable with the challenges that come with it.
I am willing to travel and stay on site for extended periods of time if necessary.
I understand the importance of thorough testing and commissioning and am committed to ensuring that the work is done properly, regardless of location.
I am familiar with the necessary safety protocols and pro...read more

Asked in Voltech Engineers Global

Q. What about E-mobility?
E-mobility refers to the use of electric vehicles and related infrastructure for transportation.
E-mobility is a growing trend in the automotive industry.
It involves the use of electric vehicles (EVs) powered by batteries or fuel cells.
E-mobility aims to reduce carbon emissions and dependence on fossil fuels.
It requires the development of charging infrastructure, such as charging stations.
E-mobility also includes the integration of renewable energy sources for charging EVs.
Exa...read more

Asked in Capgemini Engineering

Q. What are the principles of testing?
The principles of testing involve thorough planning, clear objectives, systematic approach, documentation, and validation.
Thorough planning is essential to identify test objectives, scope, resources, and timelines.
Clear objectives help in defining what needs to be tested and the expected outcomes.
A systematic approach ensures that tests are conducted in a structured manner to achieve reliable results.
Documentation of test plans, procedures, and results is crucial for traceabi...read more

Asked in Hitachi

Q. How can you improve your knowledge?
Improving knowledge requires continuous learning and seeking new experiences.
Read books and articles on relevant topics
Attend workshops, seminars, and conferences
Take online courses and tutorials
Join professional organizations and networking groups
Seek mentorship and guidance from experienced professionals
Engage in hands-on learning and experimentation
Reflect on past experiences and learn from mistakes
Stay up-to-date with industry trends and advancements

Asked in Ambuja Neotia

Q. What is the difference between a circuit breaker and an isolator?
Circuit breaker is used to protect electrical circuits from damage caused by overload or short circuit, while isolator is used to isolate a circuit for maintenance or repair.
Circuit breaker is designed to automatically open and close the circuit in case of overload or short circuit.
Isolator is manually operated to disconnect a circuit for maintenance or repair.
Circuit breaker is a safety device, while isolator is a switching device.
Examples: MCB (Miniature Circuit Breaker) is...read more
Asked in Modpro Engineering Solutions

Q. Explain logic gates and provide their truth tables.
Logic gates are fundamental building blocks of digital circuits that perform logical operations based on input signals.
Logic gates include AND, OR, NOT, NAND, NOR, XOR, and XNOR gates.
Truth table shows the output of a logic gate for all possible input combinations.
Example: Truth table for an AND gate - Input A, Input B, Output; 0, 0, 0; 0, 1, 0; 1, 0, 0; 1, 1, 1.
Interview Experiences of Popular Companies
Calculate your in-hand salary
Confused about how your in-hand salary is calculated? Enter your annual salary (CTC) and get your in-hand salary
Reviews
Interviews
Salaries
Users