L&T Construction Assistant Manager Interview Questions and Answers

Updated 25 May 2025

14 Interview questions

An Assistant Manager was asked 2mo ago
Q. Explain the procedure of Mivan Shuttering.
Ans. 

Mivan shuttering is an aluminum formwork system used for rapid construction of concrete structures.

  • 1. Preparation: Site is cleared and foundation is laid before shuttering installation.

  • 2. Assembly: Aluminum panels are assembled on-site to create the desired shape of walls and slabs.

  • 3. Alignment: Panels are aligned and secured to ensure accuracy in dimensions.

  • 4. Concrete Pouring: Concrete is poured into the formwor...

An Assistant Manager was asked
Q. What is the density of steel, including units?
Ans. 

The density of steel is a measure of its mass per unit volume.

  • Density of steel is typically measured in units of grams per cubic centimeter (g/cm³) or kilograms per cubic meter (kg/m³).

  • The density of steel can vary depending on the specific type and composition of the steel.

  • For example, the density of carbon steel is around 7.85 g/cm³, while stainless steel has a density of about 8 g/cm³.

  • The density of steel is an...

Assistant Manager Interview Questions Asked at Other Companies

asked in Axis Bank
Q1. If you are handling cash operations, how would you manage operati ... read more
asked in JSW Steel
Q2. 1. Whats is Cooling tower performance aspects, Vacuume breaker us ... read more
asked in Jio
Q3. What are the different layers of the OSI model?
asked in Axis Bank
Q4. How would you convince a widow with existing savings to purchase ... read more
asked in Axis Bank
Q5. If a valued customer urgently needs to withdraw funds without a c ... read more
An Assistant Manager was asked
Q. Briefly describe the maintenance schedule.
Ans. 

Maintenance schedule is a plan for regular upkeep of equipment or facilities to ensure their optimal performance.

  • Maintenance schedule includes regular inspections, cleaning, lubrication, and replacement of parts as needed.

  • It helps prevent breakdowns, prolongs equipment life, and reduces repair costs.

  • Examples of maintenance schedules include daily, weekly, monthly, and annual checklists.

  • Maintenance schedules should...

An Assistant Manager was asked
Q. Elaborate VT pump installation process step by step.. How many valves & types used in Raising main? Explain about Cooling Lubrication system.
Ans. 

The VT pump installation process involves several steps. The raising main has multiple valves of different types. The cooling lubrication system is also important.

  • The VT pump installation process involves selecting the right location for the pump, preparing the foundation, and installing the pump.

  • The raising main typically has gate valves, check valves, and air release valves.

  • The cooling lubrication system is resp...

What people are saying about L&T Construction

View All
an environmental health and safety officer
1w
Job Switch Referral/Lead help!!! Designation: safety officer Current Company: ACCURATE LOGIST Pvt. Ltd Previous Company: MARKOUT SOURCING
Experience in Years: 4 years in construction safety Current CTC: 3.5LPA Expected CTC: 4.2LPA Im looking for job switch in UP/GJ/MH/MP/DL location. Any referrals or lead please contact. Email: viveksing1391999@gmail.com
Got a question about L&T Construction?
Ask anonymously on communities.
An Assistant Manager was asked
Q. How much sqm plastering done by Mason per day, concrete blocks sizes, workability, painting, gypsum work
Ans. 

The amount of sqm plastering done by a Mason per day depends on various factors such as the size of concrete blocks, workability, painting, and gypsum work.

  • The size of concrete blocks can affect the amount of plastering done per day.

  • Workability of the plastering material can also affect the speed of work.

  • Painting and gypsum work can add to the time required for plastering.

  • It is difficult to give an exact number fo...

An Assistant Manager was asked 3w ago
Q. Grade of concrete
Ans. 

Concrete grades indicate the strength and composition of concrete, essential for construction durability and safety.

  • Concrete grades are classified based on compressive strength, e.g., M20, M25, M30.

  • M20 grade concrete has a compressive strength of 20 MPa, suitable for residential buildings.

  • Higher grades like M40 are used for structures requiring high strength, such as bridges.

  • The grade is determined by the mix rati...

An Assistant Manager was asked 2mo ago
Q. Explain about construction activities
Ans. 

Construction activities encompass planning, designing, and building structures, ensuring safety and compliance with regulations.

  • Site Preparation: Clearing and leveling land before construction begins.

  • Foundation Work: Pouring concrete and laying the groundwork for stability.

  • Framing: Constructing the skeleton of the building using wood or steel.

  • Roofing: Installing the roof structure to protect the building from elem...

Are these interview questions helpful?
An Assistant Manager was asked 5mo ago
Q. Lattice tower Sub bracing design
Ans. 

Lattice tower sub bracing design involves the structural support system for the tower.

  • Sub bracing design is crucial for maintaining the stability and strength of lattice towers.

  • The design should consider factors such as wind load, weight distribution, and material strength.

  • Examples of sub bracing design elements include diagonal bracing, horizontal bracing, and cross bracing.

  • Computer-aided design software is often...

An Assistant Manager was asked
Q. Productivity of plaster work and tiles
Ans. 

The productivity of plaster work and tiles is an important factor in construction projects.

  • Productivity in plaster work can be measured by the amount of plaster applied per hour or per day.

  • Factors that can affect plaster work productivity include the skill level of the workers, the quality of materials used, and the efficiency of the tools and equipment.

  • For example, experienced plasterers may be able to apply plas...

An Assistant Manager was asked
Q. Centiler beam steel design
Ans. 

Centiler beam steel design is a method used to determine the appropriate size and shape of steel beams for structural support.

  • Centiler beam steel design involves calculating the load and span of the beam to determine the required section modulus.

  • The section modulus is then used to select the appropriate beam size from standard steel beam tables.

  • Factors such as the type of load, material properties, and safety fact...

L&T Construction Assistant Manager Interview Experiences

18 interviews found

Interview experience
5
Excellent
Difficulty level
Easy
Process Duration
Less than 2 weeks
Result
Selected Selected

I appeared for an interview in Dec 2024.

Round 1 - Technical 

(1 Question)

  • Q1. Lattice tower Sub bracing design
  • Ans. 

    Lattice tower sub bracing design involves the structural support system for the tower.

    • Sub bracing design is crucial for maintaining the stability and strength of lattice towers.

    • The design should consider factors such as wind load, weight distribution, and material strength.

    • Examples of sub bracing design elements include diagonal bracing, horizontal bracing, and cross bracing.

    • Computer-aided design software is often used...

  • Answered by AI
Interview experience
4
Good
Difficulty level
Moderate
Process Duration
2-4 weeks
Result
Selected Selected
Round 1 - Technical 

(2 Questions)

  • Q1. Related TBM Tunnelling
  • Q2. How to work in metro city with EPB machine
  • Ans. 

    To work in a metro city with an EPB machine, one must be familiar with its operation and maintenance.

    • Understand the operation of the EPB machine and follow safety protocols

    • Regularly maintain and inspect the EPB machine to ensure proper functioning

    • Coordinate with other team members and stakeholders for efficient project execution

    • Stay updated on the latest technology and advancements in EPB machines

  • Answered by AI
Round 2 - HR 

(2 Questions)

  • Q1. Discussion about qualification
  • Q2. About salary and qualification

Assistant Manager Interview Questions & Answers

user image Komal Prasad

posted on 22 Apr 2025

Interview experience
4
Good
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I appeared for an interview before Apr 2024, where I was asked the following questions.

  • Q1. Related to site work
  • Q2. Related to site equipments
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Technical 

(3 Questions)

  • Q1. Elaborate VT pump installation process step by step.. How many valves & types used in Raising main? Explain about Cooling Lubrication system.
  • Ans. 

    The VT pump installation process involves several steps. The raising main has multiple valves of different types. The cooling lubrication system is also important.

    • The VT pump installation process involves selecting the right location for the pump, preparing the foundation, and installing the pump.

    • The raising main typically has gate valves, check valves, and air release valves.

    • The cooling lubrication system is responsib...

  • Answered by AI
  • Q2. Why are you going to quit the current job?
  • Q3. What is your salary expectation?

Interview Preparation Tips

Interview preparation tips for other job seekers - Be Confident..
Be Genuine..
Listen each & every Qustion or case study & Explain properly as per practical conditions.
Interview experience
3
Average
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I appeared for an interview before May 2024, where I was asked the following questions.

  • Q1. Previous experience and work exposure
  • Q2. Boilers, pipeline pressure modulation
  • Q3. Core job calculations to procure suitable material

Interview Preparation Tips

Interview preparation tips for other job seekers - It is a dream job for Civil engineers. Think twice before joining, if you are from North India. Guys, you can't even imagine the favouritism South Indians receive in L&T. If bureaucracy frustrates you, don't join because there is too much of it in L&T.

Assistant Manager Interview Questions & Answers

user image Kumar Dhananjay

posted on 10 Jan 2025

Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
4-6 weeks
Result
Selected Selected

I applied via Naukri.com and was interviewed before Jan 2024. There was 1 interview round.

Round 1 - Technical 

(1 Question)

  • Q1. What is the process of developing an erection plan?
  • Ans. 

    Developing an erection plan involves creating a detailed strategy for the construction process.

    • Identify project requirements and objectives

    • Create a timeline for completion

    • Allocate resources and manpower

    • Coordinate with subcontractors and suppliers

    • Ensure compliance with building codes and regulations

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Be calm and focused towars your goal
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I appeared for an interview before May 2024, where I was asked the following questions.

  • Q1. Grade of concrete
  • Ans. 

    Concrete grades indicate the strength and composition of concrete, essential for construction durability and safety.

    • Concrete grades are classified based on compressive strength, e.g., M20, M25, M30.

    • M20 grade concrete has a compressive strength of 20 MPa, suitable for residential buildings.

    • Higher grades like M40 are used for structures requiring high strength, such as bridges.

    • The grade is determined by the mix ratio of ...

  • Answered by AI
  • Q2. Pilling Activity
Interview experience
4
Good
Difficulty level
Moderate
Process Duration
2-4 weeks
Result
Selected Selected

I applied via Naukri.com and was interviewed before Jun 2023. There were 2 interview rounds.

Round 1 - HR 

(1 Question)

  • Q1. Reagarding work experiences & background.
Round 2 - Technical 

(4 Questions)

  • Q1. Related to technical aspects of projects executed.
  • Q2. Concrete mix designs
  • Q3. P&M productivity - Earth works
  • Q4. Customer relationship related

Interview Preparation Tips

Interview preparation tips for other job seekers - Be confident in your answers. See the scope and technical aspects of the experience claimed.

Assistant Manager Interview Questions & Answers

user image Rohit Meragu

posted on 28 Mar 2025

Interview experience
4
Good
Difficulty level
Moderate
Process Duration
2-4 weeks
Result
Selected Selected

I appeared for an interview before Mar 2024, where I was asked the following questions.

  • Q1. Explain about construction activities
  • Ans. 

    Construction activities encompass planning, designing, and building structures, ensuring safety and compliance with regulations.

    • Site Preparation: Clearing and leveling land before construction begins.

    • Foundation Work: Pouring concrete and laying the groundwork for stability.

    • Framing: Constructing the skeleton of the building using wood or steel.

    • Roofing: Installing the roof structure to protect the building from elements.

    • ...

  • Answered by AI
  • Q2. Explain procedure of Mivan Shuttering
  • Ans. 

    Mivan shuttering is an aluminum formwork system used for rapid construction of concrete structures.

    • 1. Preparation: Site is cleared and foundation is laid before shuttering installation.

    • 2. Assembly: Aluminum panels are assembled on-site to create the desired shape of walls and slabs.

    • 3. Alignment: Panels are aligned and secured to ensure accuracy in dimensions.

    • 4. Concrete Pouring: Concrete is poured into the formwork, fi...

  • Answered by AI
Interview experience
5
Excellent
Difficulty level
Hard
Process Duration
6-8 weeks
Result
Selected Selected

I applied via Walk-in and was interviewed before Jan 2023. There was 1 interview round.

Round 1 - Technical 

(9 Questions)

  • Q1. Stairs case ralling Section and fixing process
  • Q2. Productivity of plaster work and tiles
  • Ans. 

    The productivity of plaster work and tiles is an important factor in construction projects.

    • Productivity in plaster work can be measured by the amount of plaster applied per hour or per day.

    • Factors that can affect plaster work productivity include the skill level of the workers, the quality of materials used, and the efficiency of the tools and equipment.

    • For example, experienced plasterers may be able to apply plaster m...

  • Answered by AI
  • Q3. Centiler beam steel design
  • Ans. 

    Centiler beam steel design is a method used to determine the appropriate size and shape of steel beams for structural support.

    • Centiler beam steel design involves calculating the load and span of the beam to determine the required section modulus.

    • The section modulus is then used to select the appropriate beam size from standard steel beam tables.

    • Factors such as the type of load, material properties, and safety factors a...

  • Answered by AI
  • Q4. In footing 25 mm dia bend deduction yes ya No
  • Q5. Responsibility and team' work
  • Q6. Your work at site?
  • Q7. Work permit at site
  • Q8. Density of steel with unit
  • Ans. 

    The density of steel is a measure of its mass per unit volume.

    • Density of steel is typically measured in units of grams per cubic centimeter (g/cm³) or kilograms per cubic meter (kg/m³).

    • The density of steel can vary depending on the specific type and composition of the steel.

    • For example, the density of carbon steel is around 7.85 g/cm³, while stainless steel has a density of about 8 g/cm³.

    • The density of steel is an impo...

  • Answered by AI
  • Q9. AAC block price and size details
  • Ans. 

    AAC blocks are a type of lightweight concrete blocks used in construction. They come in various sizes and prices.

    • AAC blocks are made from autoclaved aerated concrete, which is a mixture of cement, lime, sand, water, and an expanding agent.

    • The size of AAC blocks can vary, but common sizes include 600mm x 200mm x 100mm and 600mm x 200mm x 150mm.

    • The prices of AAC blocks depend on factors such as the brand, quality, and qu...

  • Answered by AI

Interview Preparation Tips

Topics to prepare for L&T Construction Assistant Manager interview:
  • Nice

L&T Construction Interview FAQs

How many rounds are there in L&T Construction Assistant Manager interview?
L&T Construction interview process usually has 1-2 rounds. The most common rounds in the L&T Construction interview process are Technical, Resume Shortlist and HR.
What are the top questions asked in L&T Construction Assistant Manager interview?

Some of the top questions asked at the L&T Construction Assistant Manager interview -

  1. How much sqm plastering done by Mason per day, concrete blocks sizes, workabili...read more
  2. Elaborate VT pump installation process step by step.. How many valves & types u...read more
  3. What is the process of developing an erection pl...read more
How long is the L&T Construction Assistant Manager interview process?

The duration of L&T Construction Assistant Manager interview process can vary, but typically it takes about less than 2 weeks to complete.

Tell us how to improve this page.

Overall Interview Experience Rating

4.2/5

based on 29 interview experiences

Difficulty level

Easy 8%
Moderate 77%
Hard 15%

Duration

Less than 2 weeks 54%
2-4 weeks 23%
4-6 weeks 15%
6-8 weeks 8%
View more
L&T Construction Assistant Manager Salary
based on 1.1k salaries
₹6 L/yr - ₹18.2 L/yr
31% more than the average Assistant Manager Salary in India
View more details

L&T Construction Assistant Manager Reviews and Ratings

based on 325 reviews

3.8/5

Rating in categories

3.8

Skill development

2.9

Work-life balance

3.7

Salary

4.2

Job security

3.3

Company culture

3.3

Promotions

3.3

Work satisfaction

Explore 325 Reviews and Ratings
Assistant Manager
1.1k salaries
unlock blur

₹6 L/yr - ₹18.2 L/yr

Senior Engineer
729 salaries
unlock blur

₹3 L/yr - ₹11.9 L/yr

Assistant Construction Manager
549 salaries
unlock blur

₹5.4 L/yr - ₹17 L/yr

Civil Site Engineer
377 salaries
unlock blur

₹1.6 L/yr - ₹8.4 L/yr

Assistant Engineering Manager
319 salaries
unlock blur

₹5.7 L/yr - ₹17 L/yr

Explore more salaries
Compare L&T Construction with

Larsen & Toubro Limited

3.9
Compare

Dilip Buildcon

4.0
Compare

Simplex Infrastructures

3.4
Compare

Power Mech Projects

3.8
Compare
write
Share an Interview