Q. What is a contour line?
Ans. 

A contour line is a line on a map connecting points of equal elevation above a given level, typically sea level.

  • Contour lines represent elevation and terrain shape on topographic maps.

  • They help visualize the steepness of slopes; closely spaced lines indicate steep terrain.

  • For example, a contour line at 100 meters connects all points that are 100 meters above sea level.

  • Contour lines can also indicate landforms like...

A Site Engineer was asked
Q. What is the density of an RCC structure?
Ans. 

The density of RCC structure typically ranges from 2200 to 2500 kg/m^3.

  • Density of RCC is influenced by the type and proportion of materials used.

  • Common density range for RCC is 2200 to 2500 kg/m^3.

  • Higher density indicates stronger and more durable RCC structure.

Site Engineer Interview Questions Asked at Other Companies

Q1. 1.BBS calculation of slab? 2.Stairs case riser and tread dimensio ... read more
Q2. What is the definition of rolling margin in the context of steel?
Q3. Which type of pipeline and standards do you follow?
Q4. design? 1.what is ASD in steel design? 2.what is special consider ... read more
Q5. What is the lapping zone of beam rebar at top and bottom...? Why ... read more
A Site Engineer was asked
Q. What is the percentage elongation of steel with a yield strength of 500?
Ans. 

The elongation % of steel fy 500 is approximately 12%.

  • Elongation % is the measure of ductility of a material.

  • It is the percentage increase in length of a material before it fractures under tension.

  • For steel fy 500, the elongation % is approximately 12%.

  • This means that the steel can stretch up to 12% of its original length before it breaks.

A Site Engineer was asked
Q. How many bags of cement are in 1 cubic meter?
Ans. 

The amount of cement required for 1 cubic meter varies depending on the concrete mix design.

  • The amount of cement needed for 1 cubic meter of concrete varies from 250kg to 600kg depending on the mix design.

  • The mix design specifies the ratio of cement to other materials like sand and aggregates.

  • For example, a mix design of 1:2:4 requires 400kg of cement per cubic meter of concrete.

  • It is important to accurately calcu...

A Site Engineer was asked
Q. What is the definition of rolling margin in the context of steel?
Ans. 

Rolling margin is the difference between the actual thickness and the minimum thickness of a steel plate.

  • Rolling margin is a term used in the steel industry to measure the thickness of a steel plate.

  • It is the difference between the actual thickness and the minimum thickness of the plate.

  • The rolling margin is important because it affects the strength and durability of the steel.

  • For example, if the rolling margin is...

A Site Engineer was asked
Q. What is slump test Curing of method
Ans. 

Slump test is a measure of the consistency of fresh concrete.

  • It is used to determine the workability of concrete.

  • The test involves filling a standard cone-shaped container with concrete and then removing the cone to see how much the concrete slumps or settles.

  • The amount of slump is measured in millimeters and indicates the wetness or dryness of the concrete.

  • Curing is the process of maintaining moisture in the conc...

Hindustan Construction Company HR Interview Questions

10 questions and answers

Q. What is your work experience in Fabrication/Erection?
Q. Why do you want to leave your current company?
Q. Can you tell me about yourself?
A Site Engineer was asked
Q. How much density of material Steel Concrete Sand
Ans. 

Density of materials: Steel - 7850 kg/m3, Concrete - 2400 kg/m3, Sand - 1600 kg/m3

  • Density of steel is higher than that of concrete and sand

  • Density of concrete varies depending on the mix design

  • Density of sand can vary depending on the source and moisture content

Are these interview questions helpful?
A Site Engineer was asked
Q. Initial setting time of cement
Ans. 

Initial setting time of cement is the time taken by cement to harden and attain a particular strength.

  • Initial setting time is determined by Vicat apparatus

  • It is the time taken for the cement to lose its plasticity and become hard

  • The standard initial setting time for ordinary Portland cement is 30 minutes

  • Factors affecting initial setting time include temperature, water-cement ratio, and type of cement

Hindustan Construction Company Site Engineer Interview Experiences

11 interviews found

Site Engineer Interview Questions & Answers

user image Dilip Kumar Sharma

posted on 28 May 2025

Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
-
  • Q1. Are you able to work at any location?
  • Ans. 

    Yes, I am flexible and willing to work at any location to meet project needs and deadlines.

    • I have previously worked on projects in remote areas, adapting to local conditions.

    • I understand the importance of being on-site for effective communication and problem-solving.

    • I am open to relocation if required, as I believe it enhances my professional growth.

    • For example, I successfully managed a site in a different city, coordi...

  • Answered by AI
  • Q2. What is a contour line?
  • Ans. 

    A contour line is a line on a map connecting points of equal elevation above a given level, typically sea level.

    • Contour lines represent elevation and terrain shape on topographic maps.

    • They help visualize the steepness of slopes; closely spaced lines indicate steep terrain.

    • For example, a contour line at 100 meters connects all points that are 100 meters above sea level.

    • Contour lines can also indicate landforms like hill...

  • Answered by AI

Site Engineer Interview Questions & Answers

user image Anonymous

posted on 20 Dec 2023

Interview experience
4
Good
Difficulty level
Moderate
Process Duration
2-4 weeks
Result
Selected Selected
Round 1 - Technical 

(1 Question)

  • Q1. What is the density of RCC structure
  • Ans. 2500 kg/ m3
  • Answered Anonymously
Interview experience
4
Good
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Walk-in and was interviewed in Apr 2023. There were 3 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - HR 

(1 Question)

  • Q1. They are asking about my work and previous work please and company including salary and benifits
Round 3 - Technical 

(2 Questions)

  • Q1. Asking about building structure work related questions and about my planing for smooth working on site,with coordination between contractor and company pmc or cleint
  • Q2. About quality quantity and site work

Interview Preparation Tips

Interview preparation tips for other job seekers - All prepared about your relevant sector interview with honesty

Site Engineer Interview Questions & Answers

user image Anonymous

posted on 12 Apr 2025

Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I appeared for an interview before Apr 2024, where I was asked the following questions.

  • Q1. Basics knowledge of site
  • Q2. Safety related questions

Interview Preparation Tips

Interview preparation tips for other job seekers - Good for life balance

Site Engineer Interview Questions & Answers

user image Anonymous

posted on 16 Sep 2022

I applied via Company Website and was interviewed in Aug 2022. There was 1 interview round.

Round 1 - Technical 

(2 Questions)

  • Q1. What is slump test Curing of method
  • Ans. 

    Slump test is a measure of the consistency of fresh concrete.

    • It is used to determine the workability of concrete.

    • The test involves filling a standard cone-shaped container with concrete and then removing the cone to see how much the concrete slumps or settles.

    • The amount of slump is measured in millimeters and indicates the wetness or dryness of the concrete.

    • Curing is the process of maintaining moisture in the concrete ...

  • Answered by AI
  • Q2. Cube test Direct Sher Test Plete lod test CBRTest

Interview Preparation Tips

Interview preparation tips for other job seekers - Manjil aur taqdeer khud hi bnani padti hai

Site Engineer Interview Questions & Answers

user image Anonymous

posted on 21 May 2023

Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Approached by Company and was interviewed before May 2022. There were 2 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - HR 

(5 Questions)

  • Q1. Tell me about ur self in brief
  • Q2. Qualifications and working experience related questions
  • Q3. Problem solving questions
  • Q4. Conditional questions
  • Q5. About concrete grade

Interview Preparation Tips

Topics to prepare for Hindustan Construction Company Site Engineer interview:
  • Works relate
  • Execution
  • Concrete
  • Bbs
  • Billing
Interview preparation tips for other job seekers - If u r experienced person then gain deep knowledge related to ur field and which are your previous working experience u have.

Site Engineer Interview Questions & Answers

user image Anonymous

posted on 30 Aug 2021

I applied via Naukri.com and was interviewed in Aug 2021. There were 3 interview rounds.

Interview Questionnaire 

1 Question

  • Q1. 32 dia 1 meter weight how much?

Interview Preparation Tips

Interview preparation tips for other job seekers - Basic questions and previous company project details must

Site Engineer Interview Questions & Answers

user image Anonymous

posted on 12 Sep 2021

Interview Questionnaire 

1 Question

  • Q1. How many techniques you often use to do your work?

Interview Preparation Tips

Interview preparation tips for other job seekers - Dedicated time on work will helps you to gain pure knowledge, which is remember for life time and helps to gain confidence to do that work perfectly. This confidence reflect by your voice and face, which is recognised by interviewer.

Site Engineer Interview Questions & Answers

user image Anonymous

posted on 28 Dec 2021

I applied via Company Website and was interviewed before Dec 2020. There were 3 interview rounds.

Interview Questionnaire 

5 Questions

  • Q1. What a term of Rolling margin on a steel?
  • Ans. Rolling margin is a difference weight of steel actual weight and theoretical weight.
  • Answered by Arvind Devrani
  • Q2. Initial setting time of cement
  • Ans. Less then 30Min.not 30 min
  • Answered by Arvind Devrani
  • Q3. Elongation % of steel fy 500
  • Ans. 14%
  • Answered by Arvind Devrani
  • Q4. How much bag of cement in 1 cubic meter
  • Ans. 28.8
  • Answered by Arvind Devrani
  • Q5. How much density of material Steel Concrete Sand

Interview Preparation Tips

Interview preparation tips for other job seekers - Technically sound interview, like sagging hogging loads moment shear, all about steel, concrete and formwork such as qty calculation and fixing procedures.

Site Engineer Interview Questions & Answers

user image Anonymous

posted on 20 Dec 2020

Interview Questionnaire 

1 Question

  • Q1.  Floor Tile thickness, types of tile, company of tile,

Top trending discussions

View All
Interview Hub
6d (edited)
anshitanegi
·
ex -
Planet Spark
When HR’s Chinese English made me drop the interview!
So, I talked to the HR yesterday about the interview. I asked Please send me the location But their English… bro I was shocked! It was like talking to someone jisne english nahi kuch ar hi seekh liya ho, if the HR’s English is this I can only imagine the rest of the company I decided to drop the interview with this chinese english😶‍🌫️
FeedCard Image
Got a question about Hindustan Construction Company?
Ask anonymously on communities.

Hindustan Construction Company Interview FAQs

How many rounds are there in Hindustan Construction Company Site Engineer interview?
Hindustan Construction Company interview process usually has 1-2 rounds. The most common rounds in the Hindustan Construction Company interview process are Technical, Resume Shortlist and HR.
How to prepare for Hindustan Construction Company Site Engineer interview?
Go through your CV in detail and study all the technologies mentioned in your CV. Prepare at least two technologies or languages in depth if you are appearing for a technical interview at Hindustan Construction Company. The most common topics and skills that interviewers at Hindustan Construction Company expect are Site Engineering, Tunnel and tbm.
What are the top questions asked in Hindustan Construction Company Site Engineer interview?

Some of the top questions asked at the Hindustan Construction Company Site Engineer interview -

  1. What a term of Rolling margin on a stee...read more
  2. How much density of material Steel Concrete S...read more
  3. How much bag of cement in 1 cubic me...read more

Tell us how to improve this page.

Overall Interview Experience Rating

4.4/5

based on 9 interview experiences

Difficulty level

Moderate 100%

Duration

Less than 2 weeks 83%
2-4 weeks 17%
View more
Hindustan Construction Company Site Engineer Salary
based on 210 salaries
₹2.7 L/yr - ₹7.2 L/yr
27% more than the average Site Engineer Salary in India
View more details

Hindustan Construction Company Site Engineer Reviews and Ratings

based on 68 reviews

3.9/5

Rating in categories

4.2

Skill development

3.9

Work-life balance

3.8

Salary

4.3

Job security

3.9

Company culture

3.4

Promotions

3.9

Work satisfaction

Explore 68 Reviews and Ratings
Site Engineer
210 salaries
unlock blur

₹2.7 L/yr - ₹7.2 L/yr

Civil Site Engineer
140 salaries
unlock blur

₹3.3 L/yr - ₹7.2 L/yr

Quantity Surveyor
52 salaries
unlock blur

₹3.3 L/yr - ₹7.2 L/yr

Civil Engineer
45 salaries
unlock blur

₹2.7 L/yr - ₹6 L/yr

Manager
44 salaries
unlock blur

₹10.1 L/yr - ₹18.5 L/yr

Explore more salaries
Compare Hindustan Construction Company with

L&T Construction

4.0
Compare

Tata Projects

4.2
Compare

Simplex Infrastructures

3.4
Compare

ITD Cementation India

4.2
Compare
write
Share an Interview