Hydrotest procedure is a process of testing the strength and integrity of a pressure vessel or pipeline by filling it with water and pressurizing it.
The vessel or pipeline is filled with water and pressurized to a specified level
The pressure is held for a specified amount of time to check for leaks or deformations
The test is usually performed before commissioning or after repairs
The test pressure and duration are deter...
HDD procedure refers to the process of installing and configuring a hard disk drive in a computer system.
Ensure the HDD is compatible with the computer system
Physically install the HDD in the appropriate bay
Connect the necessary cables to the HDD and motherboard
Configure the HDD in the BIOS settings
Format the HDD and install the operating system
Test the HDD for proper functionality
I applied via Approached by Company and was interviewed before Jun 2021. There were 2 interview rounds.
I applied via Naukri.com and was interviewed before Sep 2020. There were 4 interview rounds.
When faced with a shortage of material received, we take immediate action to address the issue and minimize any negative impact.
Contact the supplier to inform them about the shortage and request immediate resolution
Check inventory records and cross-verify with the supplier's delivery documentation
Investigate the cause of the shortage, such as shipping errors or miscommunication
Implement measures to prevent future short...
Various SAP T codes for Issues
MB21 - Create Reservation
MB1A - Goods Withdrawal
MB1B - Transfer Posting
MB1C - Other Goods Receipts
MB1E - Create Stock Transport Order
MB1F - Goods Issue
MB1H - Maintain Reservation
MB1T - Transfer Posting
MB1A - Goods Withdrawal
MB1B - Transfer Posting
MB1C - Other Goods Receipts
MB1E - Create Stock Transport Order
MB1F - Goods Issue
MB1H - Maintain Reservation
I appeared for an interview before May 2020.
To fix the rate of 1 cum metre RCC for M10 and M20, factors like material cost, labor cost, equipment cost, and overheads need to be considered.
Determine the cost of materials required for 1 cum metre RCC for M10 and M20
Calculate the labor cost involved in the construction process
Consider the cost of equipment required for the construction process
Include overheads like transportation, insurance, and taxes
Compare the ra...
I applied via Company Website and was interviewed in Feb 2020. There was 1 interview round.
I applied via Approached by Company and was interviewed before Sep 2021. There were 3 interview rounds.
I applied via Walk-in and was interviewed before Jan 2022. There were 3 interview rounds.
I applied via LinkedIn and was interviewed before Nov 2022. There were 3 interview rounds.
General communication skills
posted on 24 Mar 2023
I applied via Naukri.com and was interviewed before Mar 2022. There were 2 interview rounds.
REACH compliance material refers to substances that comply with the European Union's REACH regulation.
REACH stands for Registration, Evaluation, Authorization, and Restriction of Chemicals.
REACH compliance material refers to substances that have been registered with the European Chemicals Agency (ECHA) and meet the requirements of the REACH regulation.
These substances are considered safe for use in the European Union.
E...
based on 1 interview experience
Difficulty level
Duration
based on 1 review
Rating in categories
Assistant Engineer
24
salaries
| ₹1.5 L/yr - ₹4.8 L/yr |
Assistant Manager
22
salaries
| ₹4.8 L/yr - ₹9.6 L/yr |
Senior Engineer
16
salaries
| ₹3.3 L/yr - ₹8.1 L/yr |
Accounts Officer
11
salaries
| ₹2.1 L/yr - ₹5.6 L/yr |
Deputy Manager Information Technology
9
salaries
| ₹7.1 L/yr - ₹8 L/yr |
L&T Construction
Tata Projects
Simplex Infrastructures
ITD Cementation India