Rajhans (Desai-Jain) Group QS Engineer Interview Questions and Answers

Updated 16 Aug 2024

Rajhans (Desai-Jain) Group QS Engineer Interview Experiences

1 interview found

QS Engineer Interview Questions & Answers

user image Anonymous

posted on 16 Mar 2024

Interview experience
2
Poor
Difficulty level
Easy
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Naukri.com and was interviewed in Jul 2024. There were 3 interview rounds.

Round 1 - HR 

(1 Question)

  • Q1. Salary expectations and all
Round 2 - Technical 

(1 Question)

  • Q1. What is the rolling margin in steel consumption
  • Ans. 

    Rolling margin in steel consumption refers to the percentage of excess steel ordered to account for potential wastage during the manufacturing process.

    • Rolling margin is typically around 5-10% of the total steel consumption.

    • It helps to ensure that there is enough steel available to complete a project without running out.

    • Factors such as the complexity of the project and the experience of the manufacturer can influence th...

  • Answered by AI
Round 3 - One-on-one 

(1 Question)

  • Q1. Family Background

Top trending discussions

View All
Interview Tips & Stories
2w (edited)
timepasstiwari
·
A Digital Markter
Nailed the interview, still rejected
Just had the BEST interview ever – super positive and encouraging! But got rejected. Interviewer said I was the most prepared, knew it was a full-time role (unlike others), and loved my answers. One of my questions was even called "the best ever asked!" He showed me around, said I was exactly what they wanted, and would get back by Friday. I was so hyped! Then today, I got the rejection email. No reason given, just "went with someone else." Feels bad when your best isn't enough. Anyone else been there? How'd you cope?
Got a question about Rajhans (Desai-Jain) Group?
Ask anonymously on communities.

Interview questions from similar companies

Interview experience
4
Good
Difficulty level
Hard
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Company Website and was interviewed in Apr 2023. There were 3 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Don’t add your photo or details such as gender, age, and address in your resume. These details do not add any value.
View all tips
Round 2 - Technical 

(3 Questions)

  • Q1. Any technical questions ask me
  • Q2. Difrance between OPC cement and PPC cement
  • Ans. 

    OPC cement is made from limestone and clay, while PPC cement is made from fly ash and clay.

    • OPC cement has higher strength and is used for construction of high-rise buildings and bridges.

    • PPC cement has better workability and is used for plastering and finishing works.

    • PPC cement is more eco-friendly as it uses industrial waste as a raw material.

    • OPC cement is costlier than PPC cement.

    • OPC cement is commonly used in areas w...

  • Answered by AI
  • Q3. What is two way slab
  • Ans. 

    A two way slab is a type of reinforced concrete slab that is supported by beams on all four sides.

    • Two way slab is used in buildings with large column spacing

    • It is designed to resist both positive and negative bending moments

    • It is commonly used in parking garages, commercial buildings, and residential buildings

    • Two way slab is more economical than one way slab for larger spans

  • Answered by AI
Round 3 - Assignment 

Dgijvcctuhgcvh hjjcc ghjj

QS Engineer Interview Questions Asked at Other Companies

Q1. Basic specifications of Plastering, How much Deductions are to be ... read more
Q2. What is FDD what is the density of soil Loose and Compacted?
Q3. What is the IS code for BBS and Measurements?
Q4. What is a DOL Starter?
Q5. If the cross section of a 1 km road consists of WMM and GSB layer ... read more
Interview experience
4
Good
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Don’t add your photo or details such as gender, age, and address in your resume. These details do not add any value.
View all tips
Round 2 - Aptitude Test 

Technically and mathematics and our I q test

Round 3 - HR 

(3 Questions)

  • Q1. Technically and basically
  • Q2. What about the drawing and detail of project and quantity how can be measure
  • Ans. 

    Measurements for project drawings and quantities can be determined through detailed analysis and calculations.

    • Measurements can be taken directly from the project drawings using scales and measuring tools.

    • Quantities can be calculated based on the dimensions provided in the drawings.

    • Software tools like AutoCAD and Revit can also be used to accurately measure quantities and dimensions.

    • Bill of Quantities (BOQ) can be prepa...

  • Answered by AI
  • Q3. Read the drawing proper and clear the all demarcation and prepare planning

Interview Preparation Tips

Interview preparation tips for other job seekers - Be prepare confidential and fresh mind don't be afraid
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Naukri.com and was interviewed before Aug 2023. There was 1 interview round.

Round 1 - One-on-one 

(6 Questions)

  • Q1. Use of shunt relay in acb.
  • Ans. 

    A shunt relay in an ACB is used to provide protection against overcurrents by diverting excess current away from the main circuit.

    • Shunt relay is connected in parallel with the main circuit of the ACB.

    • It detects overcurrents and activates to divert the excess current through a shunt path.

    • This helps in protecting the main circuit from damage due to overcurrents.

    • Shunt relays are commonly used in Air Circuit Breakers (ACBs...

  • Answered by AI
  • Q2. What is coc in hvac.
  • Ans. 

    CoC in HVAC stands for Certificate of Conformance, which is a document certifying that a product meets specified requirements.

    • CoC in HVAC is a Certificate of Conformance that ensures a product meets specific requirements.

    • It is often required in HVAC projects to ensure quality and compliance.

    • CoC may include details such as product specifications, testing results, and manufacturer information.

  • Answered by AI
  • Q3. What is Biological oxygen demand and Carbonic oxygen demand in STP Plant.
  • Ans. 

    Biological oxygen demand (BOD) and Chemical oxygen demand (COD) are important parameters in wastewater treatment plants.

    • Biological oxygen demand (BOD) is a measure of the amount of dissolved oxygen needed by aerobic biological organisms to break down organic material in water.

    • Carbonaceous oxygen demand (COD) is a measure of the amount of oxygen required to oxidize all the organic and inorganic matter in water.

    • BOD is a ...

  • Answered by AI
  • Q4. What is voltage monitoring relay.
  • Ans. 

    A voltage monitoring relay is a device that monitors voltage levels and triggers an alarm or protective action if the voltage exceeds or falls below a set threshold.

    • Monitors voltage levels in electrical systems

    • Triggers alarm or protective action if voltage exceeds or falls below set threshold

    • Used to protect equipment from damage due to voltage fluctuations

  • Answered by AI
  • Q5. Working principle of wtp plant.
  • Ans. 

    WTP plant works on the principle of physical and chemical processes to remove impurities from water.

    • Water enters the plant and goes through processes like coagulation, flocculation, sedimentation, filtration, and disinfection.

    • Coagulation involves adding chemicals to water to make impurities clump together.

    • Flocculation helps in forming larger particles called floc for easier removal.

    • Sedimentation allows the floc to sett...

  • Answered by AI
  • Q6. What is your daily and monthly Reports.
  • Ans. 

    I provide daily and monthly reports on project progress, issues, and key metrics to track performance.

    • Daily reports include updates on tasks completed, challenges faced, and plans for the next day.

    • Monthly reports summarize overall progress, budget status, and any potential risks or delays.

    • Reports may also include key performance indicators (KPIs) such as project milestones achieved, budget variance, and resource utiliz...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - keep mind relax interview time. And focus your daily work activities .
Interview experience
4
Good
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Approached by Company and was interviewed in Mar 2023. There were 3 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Technical 

(1 Question)

  • Q1. LT Side Equipments
Round 3 - HR 

(1 Question)

  • Q1. Introduction & Salary
Interview experience
3
Average
Difficulty level
-
Process Duration
-
Result
-
Round 1 - HR 

(2 Questions)

  • Q1. What your current salary
  • Q2. Why di you want to change

Interview Preparation Tips

Interview preparation tips for other job seekers - Please be focus on LinkedIn. It was a great Platform for searching a Job.

Interview Questionnaire 

2 Questions

  • Q1. What projects i had done in Bachelors?
  • Ans. 

    I completed various projects during my Bachelor's degree, including a design project for a new bridge and a research project on renewable energy.

    • Designed a new bridge using CAD software

    • Researched and implemented renewable energy sources on campus

    • Collaborated with classmates on a group project to improve campus sustainability

  • Answered by AI
  • Q2. Where i did my 6 months internship?
  • Ans. 

    I completed my 6 months internship at ABC Engineering Firm, where I gained hands-on experience in project management and design.

    • Internship at ABC Engineering Firm

    • Focused on project management and design

    • Hands-on experience gained

  • Answered by AI

Interview Preparation Tips

Round: Technical Interview
Experience: I was fresher, so they usually ask me about my university projects and my final training.
Tips: It will be good if you relate your projects with the company profile.

Are these interview questions helpful?

I applied via Referral and was interviewed in Jan 2020. There were 3 interview rounds.

Interview Questionnaire 

1 Question

  • Q1. Previous project breif and some technical from fire protection system and electrical.

Interview Preparation Tips

Interview preparation tips for other job seekers - Interview it was good and the most important thing i was shared a true answer regarding previous project, i will very thankfull to mr.kunal sharma who has shared my resume to cushman.tx....

Interview Questionnaire 

1 Question

  • Q1. Quality related questions

I applied via Referral and was interviewed before Jan 2021. There was 1 interview round.

Interview Questionnaire 

2 Questions

  • Q1. Intrudes your self.
  • Q2. Tell me about your skill

Interview Preparation Tips

Interview preparation tips for other job seekers - Overall good, all about intrudes myself. Describe my work experience. Telling all my technical skills.

Rajhans (Desai-Jain) Group Interview FAQs

How many rounds are there in Rajhans (Desai-Jain) Group QS Engineer interview?
Rajhans (Desai-Jain) Group interview process usually has 3 rounds. The most common rounds in the Rajhans (Desai-Jain) Group interview process are HR, Technical and One-on-one Round.

Tell us how to improve this page.

Overall Interview Experience Rating

2/5

based on 1 interview experience

Difficulty level

Easy 100%

Duration

Less than 2 weeks 100%
View more

Interview Questions from Similar Companies

JLL Interview Questions
4.1
 • 406 Interviews
CBRE Interview Questions
4.1
 • 298 Interviews
NoBroker Interview Questions
3.1
 • 253 Interviews
Colliers India Interview Questions
3.9
 • 74 Interviews
Novel Office Interview Questions
4.1
 • 68 Interviews
K Raheja Corp Interview Questions
4.3
 • 52 Interviews
Knight Frank Interview Questions
4.1
 • 49 Interviews
Omaxe Interview Questions
4.1
 • 36 Interviews
View all
Rajhans (Desai-Jain) Group QS Engineer Salary
based on 5 salaries
₹4.5 L/yr - ₹5 L/yr
6% less than the average QS Engineer Salary in India
View more details

Rajhans (Desai-Jain) Group QS Engineer Reviews and Ratings

based on 1 review

2.0/5

Rating in categories

1.0

Skill development

2.0

Work-life balance

1.0

Salary

1.0

Job security

1.0

Company culture

2.0

Promotions

1.0

Work satisfaction

Explore 1 Review and Rating
Civil Site Engineer
11 salaries
unlock blur

₹2.5 L/yr - ₹4 L/yr

Junior Engineer
9 salaries
unlock blur

₹3 L/yr - ₹5 L/yr

Engineer
8 salaries
unlock blur

₹3.9 L/yr - ₹5.3 L/yr

Senior Engineer
7 salaries
unlock blur

₹5.8 L/yr - ₹9.6 L/yr

Project Manager
6 salaries
unlock blur

₹12.6 L/yr - ₹15 L/yr

Explore more salaries
Compare Rajhans (Desai-Jain) Group with

JLL

4.1
Compare

CBRE

4.1
Compare

NoBroker

3.1
Compare

Cushman & Wakefield

4.1
Compare
write
Share an Interview