  • Q1. How to work then fail the plan
  • Ans. 

    Reassess the situation, identify what went wrong and create a new plan or adjust existing.

  • Answered Anonymously
  • Q2. Any project is budget low and how to effectively complete
  • Ans. 

    Priorities task, seek free or low cost goal, negotiable with vendor and to flexible and adaptable.scope management

  • Answered Anonymously
  • Q3. How to manage labour and materials
  • Ans. 

    Planning procurement, tracking and control the resources to optimize efficieny and cost effectiveness

  • Answered Anonymously
  • Q4. How to solve problems
  • Q5. How to maintain quality

Top trending discussions

View All
Interview Hub
6d (edited)
anshitanegi
·
ex -
Planet Spark
When HR’s Chinese English made me drop the interview!
So, I talked to the HR yesterday about the interview. I asked Please send me the location But their English… bro I was shocked! It was like talking to someone jisne english nahi kuch ar hi seekh liya ho, if the HR’s English is this I can only imagine the rest of the company I decided to drop the interview with this chinese english😶‍🌫️
FeedCard Image
Got a question about HCC Infrastructure?
Ask anonymously on communities.

Interview questions from similar companies

I appeared for an interview in Aug 2019.

Interview Questionnaire 

4 Questions

  • Q1. How many types of structure
  • Ans. 

    There are various types of structures, including buildings, bridges, dams, tunnels, and towers.

    • Structures can be classified based on their purpose, design, and materials used.

    • Buildings can be further classified into residential, commercial, and industrial structures.

    • Bridges can be classified into beam, arch, suspension, and cable-stayed bridges.

    • Dams can be classified into gravity, arch, buttress, and embankment dams.

    • Tu...

  • Answered by AI
  • Q2. What is density
  • Ans. 

    Density is the measure of mass per unit volume of a substance.

    • It is a physical property of matter.

    • It is calculated by dividing the mass of a substance by its volume.

    • Units of density include kg/m³, g/cm³, and lb/ft³.

    • Density can be used to identify substances and determine their purity.

    • For example, gold has a density of 19.3 g/cm³, while aluminum has a density of 2.7 g/cm³.

  • Answered by AI
  • Q3. How many types of density construction
  • Ans. 

    There are two types of density construction: compacted and loose.

    • Compacted density construction involves compressing the material to increase its density, such as in road construction.

    • Loose density construction involves leaving the material in its natural state, such as in landscaping.

    • The type of density construction used depends on the intended use of the material and the desired level of compaction.

    • Other factors that...

  • Answered by AI
  • Q4. Which types of tests construction joint
  • Ans. 

    Tests for construction joints include visual inspection, water tightness test, and load transfer test.

    • Visual inspection to check for proper joint alignment and sealant application

    • Water tightness test to ensure no water leakage through the joint

    • Load transfer test to verify the joint can handle the intended load

    • Other tests may include pull-out test, shear test, and compression test

    • Testing frequency and methods may vary d...

  • Answered by AI

Skills evaluated in this interview

Project Engineer Interview Questions Asked at Other Companies

asked in Wipro
Q1. Triangle Star Pattern Task Your task is to print a triangle patte ... read more
asked in Wipro
Q2. Encode The String Problem Statement Given a string S of length N, ... read more
asked in Wipro
Q3. Given a starting time, find the minimum number of minutes needed ... read more
asked in Wipro
Q4. Binary to Decimal Conversion Challenge Transform a given binary n ... read more
asked in Wipro
Q5. Mindbending Product Problem Statement You are given an array ARR ... read more

Interview Questionnaire 

1 Question

  • Q1.  Floor Tile thickness, types of tile, company of tile,

I applied via Company Website and was interviewed before Dec 2020. There were 3 interview rounds.

Interview Questionnaire 

5 Questions

  • Q1. What a term of Rolling margin on a steel?
  • Ans. Rolling margin is a difference weight of steel actual weight and theoretical weight.
  • Answered by Arvind Devrani
  • Q2. Initial setting time of cement
  • Ans. Less then 30Min.not 30 min
  • Answered by Arvind Devrani
  • Q3. Elongation % of steel fy 500
  • Ans. 14%
  • Answered by Arvind Devrani
  • Q4. How much bag of cement in 1 cubic meter
  • Ans. 28.8
  • Answered by Arvind Devrani
  • Q5. How much density of material Steel Concrete Sand

Interview Preparation Tips

Interview preparation tips for other job seekers - Technically sound interview, like sagging hogging loads moment shear, all about steel, concrete and formwork such as qty calculation and fixing procedures.

Interview Questionnaire 

1 Question

  • Q1. Site related

I applied via Naukri.com and was interviewed in Aug 2021. There were 3 interview rounds.

Interview Questionnaire 

1 Question

  • Q1. 32 dia 1 meter weight how much?

Interview Preparation Tips

Interview preparation tips for other job seekers - Basic questions and previous company project details must
Be interview-ready. Browse the most asked HR questions.
illustration image

I applied via Naukri.com and was interviewed in Jan 2021. There were 3 interview rounds.

Interview Questionnaire 

2 Questions

  • Q1. Precommissioning test of transformers
  • Ans. 

    Precommissioning tests of transformers ensure proper functioning and safety before energizing.

    • Visual inspection of transformer and its components

    • Measurement of insulation resistance

    • Measurement of winding resistance

    • Verification of transformer ratio and polarity

    • Verification of oil level and quality

    • Testing of protective devices

    • Verification of grounding

    • Functional testing of cooling system

    • Verification of nameplate data

  • Answered by AI
  • Q2. 11kv & 33kv overhead power line distribution
  • Ans. 

    11kv & 33kv overhead power line distribution

    • 11kv and 33kv are common voltage levels for overhead power lines

    • Overhead power lines are used to distribute electricity from power stations to consumers

    • The voltage level determines the distance the power can be transmitted and the size of the conductors needed

    • Proper insulation and grounding is important for safety

    • Maintenance and inspection of the lines is necessary to ensure ...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - this interview was based on electrical basic concepts for practical site works.
Are these interview questions helpful?

I applied via Walk-in and was interviewed in Nov 2021. There was 1 interview round.

Interview Questionnaire 

2 Questions

  • Q1. What do you know about Grab & the Pipeline?
  • Ans. 

    Grab is a Southeast Asian ride-hailing, food delivery, and financial services company. The Pipeline is a program to develop tech talent.

    • Grab is headquartered in Singapore and operates in 8 countries.

    • It offers various services like ride-hailing, food delivery, and financial services.

    • The Pipeline is a program to develop tech talent in Southeast Asia.

    • It provides training and mentorship to aspiring tech professionals.

    • The p...

  • Answered by AI
  • Q2. What are you doing about wtp
  • Ans. 

    I am currently overseeing the construction and installation of the WTP equipment.

    • Coordinating with the project team to ensure timely completion of the WTP

    • Ensuring compliance with safety regulations and quality standards

    • Conducting regular inspections and tests to ensure proper functioning of the equipment

    • Addressing any issues or concerns that arise during the construction process

    • Collaborating with suppliers and contract...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - I have 2 years experience in Di & Harpe Pipeline
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Technical 

(3 Questions)

  • Q1. About last company works
  • Q2. About steel and concrete
  • Q3. Handling labours and supervisors
Round 3 - HR 

(2 Questions)

  • Q1. About last paid salary
  • Q2. 1)Marital status 2) accomodation

I applied via Walk-in and was interviewed in Aug 2022. There were 2 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Technical 

(2 Questions)

  • Q1. Steel and SHUTTERING, project management
  • Q2. Hook lenght, deduction of steel in bends

Interview Preparation Tips

Interview preparation tips for other job seekers - Be positive always , face with your knowledge and attitude

HCC Infrastructure Interview FAQs

What are the top questions asked in HCC Infrastructure Project Engineer interview?

Some of the top questions asked at the HCC Infrastructure Project Engineer interview -

  1. Any project is budget low and how to effectively compl...read more
  2. How to manage labour and materi...read more
  3. How to maintain qual...read more

Tell us how to improve this page.

Overall Interview Experience Rating

4/5

based on 1 interview experience

Civil Site Engineer
16 salaries
unlock blur

₹2.9 L/yr - ₹5.8 L/yr

Civil Engineer
13 salaries
unlock blur

₹2.4 L/yr - ₹6.5 L/yr

Assistant Manager
8 salaries
unlock blur

₹8.5 L/yr - ₹15 L/yr

Senior Legal Officer
6 salaries
unlock blur

₹9.7 L/yr - ₹19.8 L/yr

Senior Engineer
6 salaries
unlock blur

₹6.8 L/yr - ₹11.4 L/yr

Explore more salaries
Compare HCC Infrastructure with

L&T Construction

4.0
Compare

Simplex Infrastructures

3.4
Compare

ITD Cementation India

4.2
Compare

Ashoka Buildcon

4.1
Compare
write
Share an Interview